|
NOTES AND
EXTRACTS
ON THE HISTORY OF THE
LONDON &
BIRMINGHAM RAILWAY
CHAPTER 7
CONSTRUCTION ―
CAMDEN TOWN TO CHEDDINGTON
INTRODUCTION
“It is not a little curious to turn back,
and watch the first beginnings of a work of such magnitude as this
railway, which will cost more than £5,000,000. In November,
1830, there was to be one line of rails only, and the work was to be
done for £6,000 per mile. The capital was then one million and
a quarter, and no greater velocity contemplated than eight miles an
hour. Shares got up to nine and ten premium on the prospectus,
at which many hundreds were sold. Then it was determined to
have two lines; and at that announcement the shares fell directly to
a discount . . . . We wonder that the speculators of those days
would have thought, if they could then have been informed what the
real cost of the present two lines would be. One thing is
certain, there would not have been a railway between London and
Birmingham for many a year.”
The History of the Railway Connecting London and
Birmingham, Peter Lecount (1839). |

|
Originally planned for completion in September 1837 within a budget
of £2.5M, the London and Birmingham Railway was at the time and in
every sense the largest civil engineering project yet undertaken in
the United Kingdom:
“Up to that time no railway of similar
magnitude had been attempted. The line from Liverpool to
Manchester was by comparison a trifling work. Its length was
little more than a quarter of the length of the new road, and its
most important works, including the Sankey viaduct (with nine arches
each of fifty feet span thrown over the Sankey valley, and running
seventy feet above the Sankey canal), its principal tunnel, 2,250
yards long, and its firm highway over the bogs of Parr Moss and Chat
Moss, are in respect of magnitude not to be compared with the Kilsby
tunnel, the Blisworth cutting, and the Wolverton embankment and
viaduct. A man of iron nerve would have experienced some
uneasiness at the commencement of such an undertaking.”
The Life of
Robert Stephenson, John Cordy Jeaffreson (1866).
Jeaffreson might have included in his list
of Stephenson’s more daunting challenges the Primrose Hill and
Watford tunnels, and the Tring Cutting, although a great deal of
heavy engineering was needed elsewhere to overcome Nature’s
obstacles while maintaining the line’s 1:330 (16 feet to the mile)
ruling gradient.
It might assist those unfamiliar with the
terrain to list the main geographical features that required civil
engineering solutions in the form of embankments, cuttings,
viaducts, bridges and tunnels. In their guide to the London
and Birmingham Railway, Roscoe and Lecount describe the landscape
thus:
|
“The country between London and Birmingham
is a series of basins or low districts, separated from each other by
considerable ridges of hills; the object to be gained was,
therefore, to cross the valleys at as high a point as possible, and
the hills at as low a one . . . . The whole will, therefore, stand
thus:―
1. The basin
at London formed by the Thames. 2. The summit at Oxhey, near the
division of the counties of Middlesex and Hertford. 3. The basin
of the Colne river. [Watford]
4. The summit at Tring. 5. The basin of the Ouse, near Stoney
Stratford.
[Wolverton] 6. The summit at
Blisworth, opposite Towcester. 7. The basin formed at Weedon by
the streams flowing into the River Nene at Northampton. 8. The
summit at Kilsby, opposite Daventry. 9. The basin of the River
Avon, crossed near Wolston, about five miles south of Coventry.
10. The summit of the Meriden ridge. 11. The basin at Birmingham
formed by the river Rea, which flows into the Tame. . . .
. . . . Although
there were found during the progress of this great work numerous and
severe difficulties, there was nothing to indicate anything like
what was experienced, and without expending vast sums in boring,
they could never have been anticipated.”
The London and
Birmingham Railway, Roscoe and Lecount (1839). |
The London and Birmingham was planned to open at the same time as
the Grand Junction Railway (sketch
map), the two lines sharing a terminus at Curzon Street.
But great difficulty in overcoming the large bed of quicksand found
at the southern end of the Kilsby Tunnel in Northamptonshire delayed
completion of the London and Birmingham line, and it was over 12
months after the Grand Junction Railway had arrived in Birmingham
(the GJR opened for business on 4th July 1837) before a through
service between London and the North-West was established.
Construction of the London and Birmingham Railway commenced at both
ends:
“LONDON
AND BIRMINGHAM
RAILWAY ― The average number of workmen
employed on the line during the early part of the present summer was
about 12,000, and the weekly expenditure of the company about
£40,000. The quantity of earth excavated will be about 16
millions of cubic yards. The weight of iron in the rails and
chairs forming the line of way will be 38,000 tons. There will
be 290,000 stone blocks of four cubic feet each, and 75,000 of five
cubic feet each, being together 1,535,000 cubic feet, or 105,000
tons of stone under the cast iron chairs or pedestals which support
the rails, and exclusively of any used in the bridges, tunnels, &c.”
The Bucks
Herald, 23rd September 1837.
The line was opened in stages as work progressed. On 20th
July 1837, a service commenced on the section between Euston and
Boxmoor (Hemel Hempstead), which was extended to Tring on the 16th
October. The line could not be completed in time for Queen
Victoria’s coronation on the 28th June 1838, but aware of the
lucrative traffic the event would generate, on the 9th April 1838,
the Company opened the section from Tring to a temporary station at
Denbigh Hall near Bletchley, and also from Birmingham to Rugby, a
stagecoach shuttle being used to bridge the 38-mile gap. The
line was eventually opened throughout on the 17th September 1838,
the first passenger train from London to Birmingham taking 5½ hours
to complete the 112½ mile journey.
This, and the following
three chapters, summarise the main civil engineering challenges that
Stephenson and his team had to overcome in building the line.
|
――――♦――――
|
ADVERTISING FOR TENDERS
“The Directors had placed equal portions of
the line under the separate superintendence of the respective London
and Birmingham Committees . . . . The directors deemed it advisable
that the execution of the whole line should be under the direction
of one engineer, and Mr. Robert Stephenson had been appointed to the
office, and had received instructions to stake out the line without
delay. The Directors had reason to believe that the railway
will be completed in about four years. The plan on which the
work is to be carried on is as follows:―
1st. That those
parts of the line which require the longest time for execution shall
be commenced first, and the rest in succession, so that the whole
may be completed at the same time.
2nd. That the purchase of
the land shall be made with reference to this arrangement.
3d. That the payment of the calls shall be regulated so that no part
of the capital shall be demanded before it is actually required.
4th. That the works shall be executed by contract, by open
competition.
The only
deviation from this plan is in reference to the end of the line near
London, which eleven Directors recommend should be finished with
expedition, from a conviction that the novelty and convenience of a
railway contiguous to the metropolis would excite general interest,
and prove an early and productive source of revenue to the Company.”
The first general
meeting of the Proprietors, reported in The Morning Post,
20th September, 1833.

Stephenson spent the time between the
passage of the London and Birmingham Railway Bill (May 1833) and the
letting of the first three contracts (May 1834) assembling his
project team, levelling and staking out the course of the line, and
drawing up plans and specifications for every aspect of the work:
“The engineer wished to
ascertain with accuracy the amount of the work before
him. To effect this, before cutting a turf, he
went over every inch of ground, and endeavoured to
calculate the exact cost of every operation necessary
for the accomplishment of his task . . . . In laying
down the Liverpool and Manchester Railway, George
Stephenson had at the outset of the undertaking only a
general notion of the labour before him. The
details were not considered till their consideration
could no longer be deferred. Robert Stephenson saw
that this plan of leaving each day to take care of its
own evils was little calculated for so vast an
undertaking as the London and Birmingham line.”
The Life of Robert Stephenson, John Cordy Jeaffreson
(1866).
With these preliminaries complete, the
Company was in a position to advertise for tenders to undertake the
work, which had been divided into sections, their extent depending
on the complexity of the task. For the reasons stated above,
the Board stipulated that work was to commence at the London end of
the line:
“In their former report, the Directors
announced the appointment of Mr. Robert Stephenson, as Engineer in
Chief. They have since succeeded, to their complete
satisfaction, in obtaining the services of a sufficient number of
skilful and scientific persons as Assistant Engineers, for
conducting the Works on every part of the Line, which has been
arranged in sub-divisions for this purpose.
Notwithstanding
the obstacles which an unfavourable season has presented to the
field operations of the Engineers, the whole of the Line from London
to Birmingham has been staked out and levelled, with the exception
of a few points, to which Mr. Stephenson is desirous of devoting his
particular attention. He has requested that the Plans and
Specifications of the Works for the first twenty miles from London
will be complete by the 1st of March.
The Directors will then
immediately advertise for Tenders for the execution of the Works on
that portion of the railway, and the Plans and Specifications for
other parts of the Line will follow in succession as shall bring the
remainder into completion, in conformity with the intention
announced in the former Report.”
Liverpool Mercury, 28th February, 1834.
Each sets of plans and specifications
were produced in triplicate, one copy being available for inspection
by potential contractors who, on the appointed day, submitted sealed
tenders for contracts in which they were interested. Tenders
were then evaluated on the basis of experience and reputation,
price, and the adequacy of the contractor’s capital for funding
construction until payment became due from the Company for completed
work. Following the award of a contract, each of the sets of
documents were signed by Stephenson and the successful contractor;
one set went to the Board, Stephenson retained a set, and a set went
to the Assistant Engineer for the district.
By August 1834,
the Company had let contracts for 42 miles of railway ― 21 miles at
each end of the line ― and the Board was confident that before the
close of the year contracts would have been let for almost 80 miles.
And so work commenced.
――――♦――――
ABANDONED CONTRACTS
If contemporary accounts are accurate,
few of the works necessary to surmount the landscape’s natural
obstacles presented exceptional problems, but those that did threw
up challenges that were more than the civil engineering contractors
of the age could handle. During the course of construction,
the Company was obliged to revoke eight of the thirty contracts and
make other arrangements. The Castlethorpe and Weedon contracts
were among those re-let to other contractors, but a further eight
were taken over by the Company’s own engineers, who then managed the
work directly and provided the wherewithal to complete it.
Under these circumstances, the Company was entitled to claim
liquidated damages for the additional costs arising from the
contractor’s failure to perform the contract, but this was not
considered feasible:
“In reviewing the extent, and particularly
the nature of the country through which the Railway passes, no
person can be surprised that a vast number of unforeseen
difficulties should arise. In the progress of the works,
difficulties were developed which defeated the sagacity of the most
experienced contractors ― which set at defiance the knowledge of the
ablest engineers . . . .
. . . . The question has been asked,
Why were not the securities of these contractors made to pay the
fine consequent on the breach of contract, and thus a portion of the
Company’s loss be recovered? The answer is plain: neither
equity nor sound policy could approve of such a line of procedure.
If the Company’s engineer, with all his experience, could not
foresee these hidden difficulties, how could a contractor estimate
them? With such discrepancies between the apparent labour, and
that which, in proceeding, was revealed, it would be a question for
a jury, or possibly the Chancellor, whether they would be liable.
The attempt to make them so would then have involved a law-suit, and
its consequent delay in the progress of the works ― a delay which
would be so injurious as to neutralise the benefits of a successful
suit ― a delay which, if the suit were unsuccessful, would have
exposed the Directors to a fearful responsibility. They,
however, acted upon the spirit of their contracts, and thus avoided
the injury and the odium which the reverse line of conduct would
have ensured.”
The
Railway Companion, from London to Birmingham,
Arthur Freeling (1839).
Thus, the cost of building the line
began to rise significantly above that estimated, although it is
probably fair to say that none of the contractors who did deliver
what was expected grew rich in the process. Speaking of the
difficulties encountered during the construction of the line, Robert
Stephenson subsequently observed:
“After the works were let, wages rose, the
prices of materials of all kinds rose, and the contractors, many of
whom were men of comparatively small capital, were thrown on their
beam-ends. Their calculations as to expenses and profits were
completely upset. Let me just go over the list. There
was Jackson, who took the Primrose Hill contract — he failed.
Then there was the next length — Nowells; then Copeland and Harding;
north of them Townsend, who had the Tring cutting; next Norris, who
had Stoke Hammond; then Soars; then Hughes: I think all of these
broke down, or at least were helped through by the directors.
Then there was that terrible contract of the Kilsby Tunnel, which
broke the Nowells, and killed one of them. The contractors to
the north of Kilsby were more fortunate, though some of them pulled
through only with the greatest difficulty. Of the eighteen
contracts in which the line was originally let, only seven were
completed by the original contractors. Eleven firms were
ruined by their contracts, which were re-let to others at advanced
prices, or were carried on and finished by the company. The
principal cause of increase in the expense, however, was the
enlargement of the stations. It appeared that we had greatly
under-estimated the traffic, and it accordingly became necessary to
spend more and more money for its accommodation, until I think I am
within the mark when I say that the expenditure on this account
alone exceeded by eight or ten fold the amount of the Parliamentary
estimate.”
The Life of
George Stephenson and of his son Robert Stephenson, Samuel
Smiles (1868).
Much had yet to be learned about
estimating and contracting for large-scale civil engineering
projects, among which was the impact on labour and material costs
arising from other railway projects competing for the same resources
― inflation was to play its part in doubling the final bill for the
line:
“Retardation of Railways by the High Price
of Labour. ― Owing to the great demand for labour the wages have
risen considerably, and increased obstacles are thrown in the way of
completing the lines which are in progress. The Birmingham,
Southampton, and other lines, we are informed, are not proceeding
with little more than half the rapidity they were. Of course
this, with the great rise in iron and other things, must tell
materially in the estimates, and tend much to retard that early
benefit the country would otherwise derive from these undertakings.
Common labourers are offered on the London and Birmingham Railway,
from fifteen to eighteen shillings per week, and masons four
shillings and sixpence per day, but even at these wages the
application for hands in many places has been unsuccessful.”
The Railway
Magazine, Vol. 1 (1836).
“From the great increase in prices, which
took place almost immediately after the letting of the works, no
less than seven [eight]
contracts were thrown on the Company’s hands, and of course these
were the most difficult and expensive parts of the works, and in
each case, the directors had to purchase all kinds of implements and
materials at a vast expense, including five locomotive engines,
while, from the times at which these seven contracts took to
complete them, there was very little possibility of transferring
these implements (technically called the Plant) from one contract to
another. This, although a very expensive process, was the only
one to be followed, or the line could not be opened under at least a
year beyond the time contemplated.”
The London and
Birmingham Railway, Roscoe and Lecount (1839).

Construction
contracts and the eventual contractors (eight having failed),
from The Life of Robert Stephenson, John Cordy Jeaffreson
(1866). |
――――♦――――
|
THE BRENT CONTRACT
On 21st April 1834, the Company let
three contracts covering the first 21 miles from London.
Messrs. Jackson and Sheddon took
the Brent (or Primrose Hill) contract, a 5¾-mile section that
included a deep cutting and tunnel under high ground adjacent to
Primrose Hill, a tunnel at Kensall Green, and a long embankment
across the Brent Valley.
The Primrose Hill Tunnel was to be
1,120 yards long, 24 feet wide, 22 feet high, with 5 shafts and
brick-lined throughout. The main problem for the contractors
lay in the nature of the terrain through which the tunnel was to be
driven, blue London clay:
“The Brent contract, a length of six miles,
was let to an experienced contractor for the sum of £119,000; the
party failed, and the Company were obliged to do the work, which in
consequence of the peculiarity of the soil, has cost them £250,000.
This contract included the Primrose-hill Tunnel, which is 1100 yards
in length, and proceeds entirely through what is termed London clay,
the most unmanageable and treacherous of all materials, the
difficulty of tunnelling through which can only be appreciated by
practical men. Unsuccessful attempts have been made to tunnel
through it at former times, the most memorable of which was the
Highgate Tunnel. The Primrose-hill Tunnel is, however, the
largest work that has ever been effectually performed through the
same material.”
The Railway
Companion, from London to Birmingham, Arthur Freeling (1838).
In the age in which the Primrose Hill
Tunnel (map) was built, tunnelling
in general remained fraught with difficulties, among which was
estimating its cost, as that at Kilsby was to prove.
Excavation alone was expensive, but especially so in London clay,
which is a tough material and very difficult to remove.
Lecount states that hatchets and cross-cut saws were the most
effective tools, for spades, pickaxes and blasting proved to be of
little use.

“The
formation over part of which we have come is called the London
clay, and constitutes the lower portion of what geologists call
the tertiary formation [from 65 million to 1.806 million
years ago]. It consists of immense
beds of argillaceous matter resting above the chalk, which latter
has, at some very remote period, formed the floor of a gulph of the
sea or bed of the mouth of a large river, which has gradually been
filled up by muddy depositions, from 300 to 600 feet thick, now
constituting the London clay. The clay with which this chalk
basin has been filled up, forms the site of the British metropolis
and neighbourhood; it extends on the north and west to the Chalk
Hills of Wiltshire, Berkshire, Oxfordshire, Buckinghamshire, and
Hertfordshire. On the east it reaches to the sea, and on the
south terminates at the North Downs.”
Osborne’s
London & Birmingham Railway Guide, E.C. and W. Osborne (1840).
A more acute difficulty associated
with London clay was already known, for some years previously the
Highgate Tunnel, which passes through the same terrain, collapsed.
Its failure was attributed to the immense pressure exerted by London
clay when exposed to air [1] and the inability of
the tunnel’s brick lining to withstand it:
“The London clay is penetrated by the
Primrose Hill Tunnel, and presents a close, compact, and dry
appearance. This tunnel was perfectly free from water, but a
more than usual thickness of brick lining was necessary, arising
from an extraordinary pressure, probably caused by the swelling of
the clay, on exposure to the atmosphere.”
The London and
Birmingham Railway, Roscoe and Lecount (1839).

Portal at
Primrose Hill Tunnel under construction, April 1837. John Cooke
Bourne.
Towards the end of 1834, the Company
was obliged to take over the work from
Jackson and Sheddon,
the contractors, who had become bankrupt.
In their place, Stephenson appointed John Cass Birkinshaw to take
over supervision:
“The London and Birmingham Railway was
commenced in the year 1834, and Mr. Birkinshaw was appointed
assistant engineer at the London or Camden Town end. But he
did not long retain that position, for the contractor having become
bankrupt, the works were carried on by the company, and Mr.
Birkinshaw, as having already had much experience, was considered by
Mr. Stephenson a proper person for their direction and management.
The heaviest works were the Primrose Hill tunnel, made through the
London clay, the open-cut tunnel at Kensal Green, and the Brent
bridge, beyond which his portion of the line did not extend far.
The works were well done, and elicited favourable remarks both from
Mr. Stephenson and from the chairman of the company.”
From an obituary
of John Cass Birkinshaw (1811-67) held by the Institution of Civil
Engineers.
|
 |
|
Section of Primrose Hill Tunnel, showing timbering
and the brick invert (bottom). |
In view of the clay’s ability to exert
substantial force as it expanded, Stephenson and Birkinshaw adopted
unusual precautions. Excavation was limited to nine feet in
advance of the tunnel’s brick lining, and very strong timbering was
used to support the arching until the brickwork was complete.
Owing to the extraordinary expansivity of the moist clay, the
pressure on the brickwork was such that it forced the mortar from
between the joints, bringing the bricks’ inner edges into contact, a
problem made worse by the local bricks having hollow surfaces that
made them unfit to bear great pressure. Lecount states in his
history of the Railway that the bricks were ground into dust and, by
degrees, the tunnel’s dimensions insensibly but irresistibly
contracted. In his biography of the Stephensons, Samuel Smiles
also refers to the problem:
|
“The pressure behind the
brickwork was so great that it made the face of the
bricks to fly off in minute chips, which covered his
[Stephenson’s]
clothes while he was inspecting the work.”
Life of George Stephenson and his son Robert Stephenson,
Samuel Smiles (1868). |
This difficulty was overcome using
very hard bricks laid in Roman cement, which, by setting hard before
the external pressure became great enough to force the bricks into
contact, enabled the whole surface of the brick to resist the
pressure, rather than just its edges. The thickness of the
brick lining was also increased in most parts of the tunnel to
twenty seven inches and the invert (an inverted arch on the tunnel
floor) to eighteen ― the invert, it appears, had been abandoned as a
cost-cutting measure:
“In the original designs for the tunnels on
the Loudon and Birmingham Railway, all the sections contained
inverts, of rather slighter
depth than the arch. In the Watford tunnel, through solid
chalk, the invert was found to be altogether unnecessary, and its
place was supplied by ordinary footings to the side walls. A
similar change, which was not only a saving of a large expense, but
a means of very considerably increasing the rate of progress of the
limiting works of the line, was accordingly attempted in the
Primrose-hill tunnel; but the hard London clay, though requiring a
pick axe to cut it, soon showed such unmistakeable menace of rising
from the floor to fill the whole excavated area, that the original
section was re-established.”
Personal
Recollections of English Engineers, F. R.
Conder (1868).
Other than the engineering problems
thrown up by London clay, inclement weather also played its part in
delaying the tunnel’s completion and the opening of the first
section of the line:
“The Directors, in their late Reports,
expressed an expectation that the first 21 miles of the railway from
London would be completed in the spring of 1837. They regret
to say that, owing to the late unexampled season, this expectation
cannot now be realised before the summer. The engineer reports
that the continued bad weather for the last four months, defeated
his calculations in a degree which no former experience could have
led him to anticipate. In some descriptions of soil this delay
could not have taken place to such an extent as in the London clay,
which is exemplified by the progress of the works on other parts of
the line, where the material is more favourable; but in the London
district the incessant falls of rain have rendered it quite
impracticable to proceed with them uninterruptedly. With the
excavations and embankments on the Primrose-hill contract he
persevered until the extra expense was such as to induce him to
suspend further operations; a step, in the propriety of which, the
Directors fully concurred.”
Report of the 7th
half-yearly General Meeting, Northampton Mercury, 18th
February 1837.

South
entrance to the Primrose Hill Tunnel by John Cooke
Bourne, 1837.
“Leaving Kentish Town on the right, and
passing under Chalk Farm bridge, we enter the Primrose Hill cutting.
If the traveller should now happen to look out from the window of
the carriage, he will behold stretching across the line the noble
entrance of the Primrose Hill tunnel. This is a bold and
massive structure, erected in that style of architecture which is
usually termed the Italian; and consists of two wings and a centre,
raised upon a rusticated basement.”
Drake’s
Road Book of the London and Birmingham Railway, James Drake (1839).
The Brent section also included the
320-yard Kensal Green Tunnel, probably the World’s first ‘cut and
cover’ railway tunnel:
“Kensal Green Tunnel: The Railway passes
under the Edgeware Road and Kilburn Wells. At Kensal Green, a
deep cutting was made to pass under the Harrow Road, at a very acute
angle; after which the channel was covered over, and the roadway
newly made. This gallery, or covered way, called the Tunnel,
at Kensal Green, is 966 feet 6 inches in length.”
The Literary
World, Vol. 2 (1840).
Judging from the absence of reports,
the tunnel appears to have been completed without serious incident,
but that cannot be said for the embankment and viaduct across the
Brent Valley:
“Here is a
slight excavation of about 150 yards, which is succeeded by an
embankment of one mile and a half in length, which is, in some
places, from 35 to 40 feet high; under it is a small tunnel, two
field bridges, and what we must call the Brent Viaduct . . . . it is
85 yards long, and consists of one main arch, and three others in
each abutment; the former is 37 feet from the level of the river
Brent, which flows through it . . . . it is in some places nearly
forty feet in height, and it contains 101,923 cubic yards of earth.”
The Railway
Companion, from London to Birmingham, Arthur Freeling (1838).
This embankment was constructed from
pieces of broken up London clay, but was not soundly compacted,
leaving fissures within the structure that gradually caused the
interior to become saturated with rainwater. The clay
softened, resulting in slippage:
“With
reference to that portion between London and Tring, the permanent
road is in tolerably good order, except on the Brent Embankment near
London and on the Colne Embankment near Watford. Both these
works have continued to subside, with scarcely any intermission,
more or less rapidly since their formation; the former from the
slippery nature of the material which composes it, the latter from
the unsoundness of its substratum in the valley of Colne.
The gradual subsidence of embankments admits of no other remedy than
maintaining the level of the railway by the constant supply of new
sound material adapted for ballasting, which in the present case
may fortunately be obtained from a convenient spot, and at a
moderate expense, for there is in the Company’s possession at the
south end of the Watford Tunnel, a large store of excellent gravel
and chalk, sufficient to meet all the demands of the line and
stations between Watford and London for some years.”
The
Mechanics’ Magazine, Volume XXVIII (1838).
Severe weather also delayed work on
the Brent Embankment (and also at Wolverton and Tring, where
excavation of the long Tring Cutting came to a standstill).
Despite these setbacks, at the General Meeting held in February 1837
the Chairman was able to inform those present that the Brent
contract was nearing completion:
“The
works of the Primrose-hill contract, which have been continued by
the Company under the direction of the engineer, are nearly
completed with the exception of the Brent embankment. The
Primrose-hill and the Kensal-green tunnels are finished and
traversed by the Company’s engines, and the permanent way is laid
through a great part of this contract. Of the embankment
on the south side of the Brent bridge, about 58,000 cubic yards
remain unfinished, to complete which, under an ordinary state of the
weather, would require three months. That portion of the
embankment which is north of the bridge is brought up to it, but not
yet raised to the railway level. On the completion of the
embankment north of the Brent, the engineer proposes to expedite the
formation of the south portion of it by making 6,000 or 8,000 cubic
yards of side cutting, thus guarding against further disappointment
as far as practicable.
From this point to Watford no work
appears to require especial mention, the completion of the Watford
tunnel and the small quantity remaining in the excavations at each
end, rendering any detailed remarks on this part of the line
unnecessary.”
Report of the 7th
half-yearly General Meeting, Northampton Mercury, 18th
February 1837.
The Primrose Hill Tunnel was
eventually completed in January 1837 at a cost of £280,000, over
twice the contract price, but despite the Chairman’s optimistic
forecast for completion of the Brent Embankment, tipping and
compacting more material to counter slippage was still proceeding in
1838.
|
――――♦――――
|
THE WATFORD EMBANKMENT AND
VIADUCTS

The ‘Bushey
Arches’ viaduct near Watford ― a public house sign, now in Watford
Museum.
The second of the London contracts
covering the section from the River Brent to the River Colne was let
to Nowell & Son. This work, which included a cutting through
the Oxhey Ridge ― the original plan being for a tunnel ―
does not appears to have presented any particular engineering
challenges:
“Mr. Stephenson reported that from the
nature of the soil at the proposed Tunnel under Oxhey Lane,
and from the comparisons of Messrs. Nowell & Sons prices for
tunnelling in the Schedule of extras and the prices of excavations,
he considered it would be for the advantage of the Company that this
portion of the Line should be made an open cutting. That
Messrs. Nowell & Sons were willing to substitute the excavation for
the Tunnelling without any additions to the sum for which they have
contracted.
Minute No. 179. Resolved that the Engineer-in-Chief be
authorised to make necessary arrangements with Messrs. Nowell &
Sons, and that the portion of land at Hatch End required for spoil
be reserved for that purpose.”
Board Minutes,
24th September 1834.
The completed Oxhey cutting impressed one travel writer sufficiently
to prompt him to pen a description:
“On the left appears Oxhey Ridge.
This ridge is part of a chain of hills which extend from Chipping
Barnet to Uxbridge, and for a considerable distance form the
boundary between Middlesex and Hertfordshire. The materials of
which they are composed are principally sand and clay; and it was on
account of the difficulty of carrying a tunnel through such a
description of ground, that the railway was made to cross them by a
cutting, notwithstanding their great elevation. In passing
through this excavation, we cannot avoid being struck with
astonishment at the immense amount of labour which its construction
must have required; it being a mile and a half in length, and in
many places between thirty and forty feet deep. It is crossed
by several bridges, the principal of which is Oxhey lane bridge, a
noble structure of three arches, but attracting attention chiefly by
its extraordinary height. A short opening which occurs
immediately after passing this bridge enables us to catch a glimpse
of Oxhey Wood; and, upon the termination of the cutting, we behold
amid some prettily wooded scenery on the left the little village of
Oxhey, with its antiquated chapel and remarkable churchyard, ―
remarkable, indeed, if we may place any credit in the asseverations
of a rustic, who solemnly assured us that its silent denizens were
wont to be buried in a bolt upright posture.”
Drake’s Road
Book of the London and Birmingham Railway, James Drake (1839)

Oxhey Lane Bridge
in a later era.
The contract also included the
southerly of the two
mainline viaducts [2] in the Colne Valley,
the London-road viaduct, known locally as the ‘Bushey Arches’.
This is a 5-arch structure of which the arch spanning the former
‘Sparrows Herne’ turnpike (Bushey Heath to Aylesbury) is the first
skew arch to the design of Assistant Engineer George Watson Buck:
“Soon after entering upon it
[the Watford embankment] the Railway goes
over the London road, by a brick viaduct of five arches, of
forty-three feet span each; they are composed of ellipses, having
voussoirs at the intrados; [3]
the centre arch is of an oblique form, in order that the course
of the road should be preserved as heretofore. This may be
thought a bad feature in a design of this kind, but it was
unavoidable, the trustees having compulsory clauses in the Act of
Parliament to compel the Company to adopt this form of arch.
The manner in which the engineer has overcome the defect in the
design is admirable, and it is scarcely perceptible to the observer:
it is a very massive structure, and cost in its erection £9,700.
The other arches are square with the line of Railway; and at either
end are retaining walls built into the embankment, making the total
length of the viaduct three hundred and seventy feet.”
The
London and Birmingham Railway, Roscoe and
Lecount (1839).

The London Road
Viaduct’s skewed arch.
|
“Mr.
Stephenson reported that one arch of the Watford Bridge is turned
and that another is nearly so, and that a third, a skew arch, is in
such a state of forwardness that he expects the whole to to
completed in two months.”
Board
minutes, 26th November 1834.. |
The London-road viaduct is followed by a 1½-mile long embankment,
the River Colne being bridged by the 5-arch ‘Colne Viaduct’ ― both
embankment and viaduct threw up engineering challenges.
The
problem that the contractors faced with the Colne embankment lay
not in the use of unsuitable material from which to form it, [4]
nor in excessively steep slopes, but in the valley’s weak
sub-stratum that was unable to withstand the loading. As with
the Brent embankment the only remedy was to continue tipping
material until the formation stabilised:
“It
has been found useless to remove the bog, on account of the water it
contains, and the only alternative is therefore to allow the
embankment to proceed and settle as it may. It is very low
near the ends, and descends rapidly and somewhat irregularly; the
men ought to be constantly cautioned against their danger in taking
off the horses from the [earth]
waggons, and are much exposed to going over. The brakes
however are simple and well managed.”
Report to the Visiting Committee, 27th and 28th May, 1836.
“The
Sub-Committee had the satisfaction to find that the Embankment at
Watford, under Messrs. Nowell's, was proceeding in conformity with
the directions of the Committee, that the Bog earth was removed and
replaced by sound material from the side sutting, and that the
embankment was in consequence assuming the necessary stability.
The difficulties at this point are not likely to retard the
completion of the first 21 miles of the Railway.”
Report to the Visiting Committee, 1st and 2nd September 1836.
“It
took nearly one million cubic yards of earth to make this
embankment, which is in some places above forty feet in height and
is the largest throughout the whole line . . . . The
whole of the land near this spot is most precarious in stability;
and the effects are clearly visible in the amazing ‘slips’ which
have taken place in the embankment across the [Colne]
valley. Oftentimes, in a very few hours, the level of the
newly-formed ground has sunk several feet, while the base of the
embankment has widened out to an enormous extent, causing infinite
labour to bring the level of the Railway back again to its original
state, and to make it solid enough for the passage of the trains;
this has caused many a sleepless night to the workmen and engineers.
The length of this embankment is about a mile and a half, and is
composed entirely of the finest materials for such a purpose ― chalk
and gravel.”
The London and Birmingham
Railway, Roscoe and Lecount (1839).

The Colne Valley
embankment and River Colne Viaduct, by John Cooke Bourne (1837).
Note the
abandoned stone sleepers, right foreground above.
And the same problem affected the
viaduct over the Colne. Both Conder and Lecount recalled the
considerable excavation that was necessary to find firm ground on
which to rest the viaduct’s piers:
“. . . . long trains of brick-carts and
timber-carriages commenced a service from the nearest canal wharf,
and piles of bricks, and heaps of half-wrought freestone from
Yorkshire quarries, began to accumulate near the waggon-building
field. Then there was a great-field day of the engineers, a
display of lines and levels and measuring tapes, an arbitrary
infringement on the turnpike road, and the foundations of the great
new viaduct were commenced. It was necessary to press this
work as rapidly as possible, as some million and more cubic yards of
embankment had to be carried over it and tipped to form the southern
portion of the great Colne Valley Embankment. For seventeen
feet the workmen had to sink, before arriving at a foundation
sufficiently firm to sustain the weight of the piers.”
Personal
Recollections of English Engineers, F. R.
Conder (1868).
“The construction of this bridge
[the viaduct]
was a work of considerable skill and labour, the foundations being
of the loosest material possible; in fact, it may almost be called a
floating bridge ― for it rests entirely on platforms of wood, having
sheet piling to protect them. The cost of its construction was
little less than £10,000.”
The
London and Birmingham Railway, Roscoe and
Lecount (1839).

The Colne
Viaduct, by John Cooke Bourne (1837).
|
――――♦――――
|
THE WATFORD TUNNEL

Watford Tunnel
face, 6th June 1837, by John Cooke Bourne.
Stephenson’s original plan was to route the line to the west of
Watford and into the Gade Valley; then, to proceed northwards in
close company with the Grand Junction Canal to Hunton Bridge where
the line would have joined the existing route. However, the
Earls of Essex and of Clarendon, landowners of the Cassiobury and
Grove estates through which the line was to pass, were implacably
opposed to this scheme (and, indeed, to the Railway as a whole).
Thus, as an alternative, George Stephenson & Son submitted a report
recommending that the line pass to the east of Watford and then
northwards through what is now the long Watford Tunnel:
“The alteration at Cassiobury as an expedient
to avoid the private grounds of Lords Essex and Clarendon is
unquestionably an expensive one, but after thorough examination of
that neighbourhood keeping in view the necessity of avoiding
Cassiobury Park and the adjoining plantation belonging to Lord Essex
we are inclined to recommend the adaption of it, though it involves
the necessity of a Tunnel.
This leads us to notice the circumstances of Tunnels occurring in
the line we are now recommending. It is certainly desirable to
avoid such mode of surmounting high grounds if it were practicable
at a moderate expense but we are induced to recommend Tunnels in
some situations when the depth of the cutting is very great in order
that the first cost of the line may be greatly diminished.”
Report dated 21st
September 1831.
In evidence given before a Committee of the House of Lords,
Stephenson expressed his feelings plainly on the need for this
deviation:
“I have been nearly two years examining the
country for the proposed line to Birmingham, which begins at Oxhey
Lane and goes from thence to the South end of Watford, through the
Colne valley, and passes the parks of Lords Clarendon and Essex,
avoiding the same by a tunnel and an acute curve, which would be
attended with no inconvenience . . . .”
Abstract of
Evidence given before a Committee of the House of Lords, June 1832.
The Watford Tunnel and its two deep
approach cuttings formed part of the contract let to Copeland and
Harding, which covered the section from the southern end of the
Colne crossing to King’s Langley:
“Just past here is the entrance to the
Watford Tunnel; it is 24 feet wide, and the crown of the arch is 25
feet high; it is ventilated by six shafts, the largest of which is a
memorial of the death of the persons buried here during the
excavation; the shaft was increased in size to get out their bodies;
the tunnel is one mile 170 yards in length; upwards 120,000 cubic
yards of earth were taken out of it.”
The
Railway Companion, from London to Birmingham,
Arthur Freeling (1839).
“. . . . I made my escape into the
wider, though more reasonable, turmoil of the tunnel. There
was no day there and no peace: the shrill roar of escaping steam;
the groans of mighty engines heaving ponderous loads of earth to the
surface; the click-clack of lesser engines pumping dry the numerous
springs by which the drift was intersected; the reverberating
thunder of the small blasts of powder fired upon the mining works;
the rumble of trains of trucks; the clatter of horses’ feet; the
clank of chains; the strain of cordage; and a myriad of other
sounds, accordant and discordant. There were to be seen miners
from Cornwall, drift-borers from Wales, pitmen from Staffordshire
and Northumberland, engineers from Yorkshire and Lancashire, navvies
— Englishmen, Scotchmen, and Irishmen — from everywhere,
muck-shifters, pickmen, barrowmen, brakes-men, banksmen, drivers,
gaffers, gangers, carpenters, bricklayers, labourers, and boys of
all sorts, ages and sizes; some engaged upon the inverts beneath the
rails, some upon the drains below these, some upon the extension of
the drifts, some clearing away the falling earth, some loading it
upon the trucks, some working like bees in cells building up the
tunnel sides, some upon the centre turning the great arches, some
stretched upon their backs putting the key-bricks to the crown — all
speaking in a hundred dialects, with dangers known and unknown
impending on every side; with commands and countermands echoing
about through air murky with the smoke and flame of burning
tar-barrels, cressets, and torches. Such was the interior of
Watford tunnel.”
‘Navvies
as they used to be’, from Household Words, Vol. XIII.,
19th January 1856.
At Watford, the terrain becomes
predominantly chalk, but soft chalk rent by gravel-filled fissures
as much as one hundred feet deep:
“The gravel is most abundant in the
neighbourhood of Watford, covering the upper chalk which in many
places it penetrates, or in other words, the large fissures or rents
in the chalk are filled with gravel, and as this latter material is
very loose and mobile, it was the occasion of much difficulty and
danger in the excavation of the Watford tunnel; for at times,
when the miners thought they were excavating through solid chalk,
they would in a moment break into loose gravel, which would run into
the tunnel with the rapidity of water, unless the most prompt
precautions were taken.”
The London and Birmingham
Railway, Roscoe and Lecount (1839).
These fissures were cut into on
several occasions, but on the 17th July 1835 there occurred an
inrush of gravel at the foot of one of the working shafts that
buried alive ten of the miners at work in the tunnel:
“The shaft in question, one of the four in
this length of tunnel (1,700 yards), is termed a gin-shaft, and has
been sunk about 90 feet below an elevated platform erected for the
purpose of removing the earth. The shaft has been very lately
sunk, and two nine-feet lengths of tunnel had been bricked, the
third being, it is stated, just mined and ready for the bricklayers.
The shaft was about to be bricked on Friday morning, between 5 and 6
o’clock, by a party consisting of five bricklayers and six
labourers, who composed what is termed the night gang; and had the
appalling event taken place a few hours afterwards, the morning gang
would have been at work, and the loss of human life must have been
awful in the extreme . . . . In loosening a portion of the wood work
previous to bricking the shaft, it is supposed the earth gave way
and buried the unfortunate men, carrying the whole of the wood work
with it . . . . The men must be buried upwards of 80 feet below the
surface of the earth, and although 60 men are actively engaged in
digging out the bodies, it is probable that six or seven days will
elapse before they are extricated.”
The Bucks
Herald, 25th July 1835.
“After more than a month of incessant
exertions on the part of Messrs. Harding and Copeland, the
contractors for the Watford line of the London and Birmingham
Railway, and a vast number of labourers who were relieved every
twelve hours, the bodies of some of the unfortunate men, who were
buried under more than eighty feet of earth, by the sudden falling
in of the shaft in Russell Wood, Levesdon Green, Watford, in this
county, have been dug out. Early on Saturday morning the
miners were enabled by crawling between the interstices made by the
fallen timbers, to see the legs of some of the sufferers, and to
know that before many more feet of the gravel and chalk had been
removed (the distance from the surface being about eighty-four feet)
they would come to the bodies . . . . At three o’clock in the
afternoon an extended hand presented itself to the view of the
bystanders, on the side of the opening opposite to that which the
first eruption of the gravel is supposed to have taken place.
The body on being cleared was found in a sitting posture, with the
head thrown back; it is presumed the poor fellow was looking upwards
at the moment he met his death, have heard the cry of “ware” from
the men at the top of the arch; his face was crushed and the legs
broken.”
The Bucks
Herald, 22nd August 1835.
In view of the risk of tunnelling
through such hazardous terrain, the workforce was reluctant to
continue. Many years later, Francis Fox, son the Charles Fox,
the tunnel’s Resident Engineer, recalled his father’s strategy for
getting the men back to work:
“Whilst engaged in the construction of the
Watford Tunnel in 1834, he received instructions to go to
Birmingham. He asked to be allowed to remain, for they were
working in very soft and dangerous ground; but his request was
declined, and he was sent to Birmingham. He had not been gone
more than a few days when a message was received that the tunnel had
fallen in, and eleven men had been killed. He immediately
hurried back, and found that there was a panic on the spot. Up
to this point is what my father himself told me, but a very old
friend of mine further related that, when the tunnel had fallen in
and had produced this panic, my father went to the works and said to
the men, ‘That tunnel has to be put through, cost what it will, and
therefore I want you men to volunteer.’ Not one of them would
do so. ‘Very well,’ he said, ‘I will do it’; and he got into
the bucket, and was just about to be lowered down the shaft, when
the ganger, using language more strong than elegant, said he ‘would
not see the master killed alone.’ He went down with him, and
these two finished the length through the dangerous ground, after
which the men returned to work.”
River, Road,
and Rail ― some engineering reminiscences, Francis Fox MInstCE
(1904).
By February 1837, the Chairman was
able to report that all that needed to be done on the Watford Tunnel
was a small amount of work on the excavations at either end. |
――――♦――――
|
KINGS LANGLEY TO CHEDDINGTON

A romantic view
over Boxmoor looking towards Berkhamsted.
The contracts for the Kings Langley to
Aldbury [5] section were let to ‘W. & L. Cubitt’,
a name connected with many notable Victorian construction projects
including the 1-mile Camden Town to Euston railway extension, and
both Euston and King’s Cross stations. Although there were no
engineering problems of note on this section, it included several
interesting features; the fine iron skew segmental arch bridge
across the Grand Junction Canal at
King’s Langley (alas, now
defaced in concrete reinforcement), a masonry skew bridge at
Boxmoor, Boxmoor embankment, the
long retaining wall adjacent to Berkhamsted Castle and the
Northchurch Tunnel.

George Watson Buck’s masonry skew arch bridge at Boxmoor.

Referring to this bridge, Roscoe and Lecount were of
the opinion that . . . .
“The science of bridge building
has, of late years, made rapid strides towards
perfection, and there are many instances where arches of
immense span have been erected; but we believe no
example exists of such an oblique arch executed in brick
work as that now under notice. The square span
across the road is twenty-one feet; but the obliquity
causes the span on the face of the arch to be lengthened
to more than thirty-nine feet; its facial form is that
of a flat segment of a circle; and the acute angle of
the quoins is chamfered off until it reaches the obtuse
angle, where it vanishes. This gives the bridge
the appearance of having one voussoir more than it
really has; and also obviates the defects which
generally attend the construction of skew bridges, by
the acute angles of the quoins being broken off or
injured, either by settlement or accidental blows.
The idea of cutting off the acute angles of such arches
emanated, we believe, from Mr. George Buck, the resident
engineer of the line from London to Tring. The
perfect manner in which the whole of the stone work, and
the spiral courses of the bricks, are executed, reflects
great credit upon the builders, Messrs. Cubitt of
London.”
At Berkhamsted . . . .
“. . . . work had begun in 1834 with a
massive earthmoving operation needed to take the line across the
outer moat of the Castle, and huge quantities of bricks were needed
to make a stable base (Birtchnell 1972, 87). The original
station (Birtchnell 1975, xiii, 22-3) was a handsome brick building
in Elizabethan style, and stood almost opposite the Castle Street
canal bridge. It was replaced in 1872 prior to the widening of the
tracks . . . . ”
Extensive
Urban Survey ― Hertfordshire: English Heritage and Hertfordshire
County Council
(2005).
Berkhamsted Castle is said to be the first building to receive what
in today’s language would be described as a ‘preservation order’.
Sections 98 and 99 of the 1833 Act stipulated that the Railway was
not to deviate from the authorised line (100 yards in either
direction was usually permitted) when passing through the grounds of
Berkhamsted Castle, neither were any structures ― except for the
necessary bridges, culverts, etc. ― to be erected, while section 100
forbad the Company from making bricks or burning lime anywhere
within the parish.

The original
Berkhamsted Station. The Grand Junction Canal is to the right in
the picture
― note the absence of platforms. At this point the Railway
passes between the Canal and Berkhamsted Castle atop the substantial
retaining wall in the foreground.
Nevertheless, the Railway cut
through the Castle’s outer gate and earthwork defences, running
atop a substantial retaining wall, the requirements for which
Brees cites as a model for specifying railway construction work.
This is an extract:
“RETAINING WALL AT BERKHAMPSTEAD CASTLE.
“This Wall is for
the purpose of retaining the Railway Embankments along the part of
the road from Berkhampstead to Berkhampstead place, immediately in
front of the Castle. Pilasters are to break forward half a
brick from the face of the wall, at a distance of 20 feet, as near
as may be, centre to centre, and they are to run flush into the
plinth at the bottom, which must project half a brick. The top
course of the Plinth must consist entirely of headers, neatly
bevelled off, and laid in cement. A piece of stone, of the
dimensions and form shown, is to stand out as a string-course from
the pilasters, and in the manner shown in the drawings, and along
the wall, at the same level, a half brick projection of equal depth
is to be continued, the bricks of which must be rubbed on the outer
surface. Where the road passes under the Railway, this
arrangement is altered, as will be seen from the drawings. A
torous moulding extending as far as the outside of the pilasters in
front of the abutments. Immediately behind the pilaster, the
wall must be broken by counterforts, of the form and dimensions
shown in the drawings, and they must be well bonded into its
substance. The footings are to be carried down 1 foot 6 inches
below the present surface, and whatever is the section of the
ground, they must in no part be formed at a less depth . . . .”
Railway
Practice: a collection of working plans and practical details,
S. C. Brees (1847).
From Berkhamsted, the line continues
northwards along the Bulbourne Valley in close company with the
Grand Junction Canal, through Northchurch and Dudswell towards its
summit and the long cutting through the depression in the ridge of
the Chilterns known as the ‘Tring Gap’:
“We now enter the Dudswell excavation; it
is in some places fifty-three feet deep, and, including the tunnel,
three quarters of a mile in length, of which the North Church Tunnel
is nearly one half; the road from Ashridge to North Church passes
over the tunnel . . . . The traveller will have observed one
peculiarity in this excavation; from the nature of the soil; and the
depth of the excavation; it was found necessary to make a platform,
or gallery, about half way up; this is about ten feet in width, and
then the slope again commences; this platform gives great security
to the slopes, and prevents their falling in; the following diagram
will give a better idea than mere description.”
The
Railway Companion, from London to Birmingham,
Arthur Freeling (1839).
Although Freeling and Roscoe both
refer to the ‘Dudswell excavation’, it is at Northchurch where the
cutting ― approaching a mile in length ― commences, deepening as it
approaches the high ground at its northern end under which it passes
through the Northchurch Tunnel. Both Freeling and Roscoe refer
to the slopes of the cutting being divided by a ‘bench’, which
Freeling depicts thus:
“The upper strata of
the Dudswell excavation are formed of wider slopes than the lower
portion, owing to a different nature of the soil; and it also has a
bench where they unite, to give security to the slopes.”
The London and Birmingham
Railway, Roscoe and Lecount (1839).

“Bench, or
Berm: a ledge left on the face of a cutting to strengthen the
same. Steep cuttings should always have ledges to support them,
particularly in canal work to prevent the mould from the upper part,
falling down into the water; chalk may also be executed at a very
steep inclination by their assistance. Ledges are likewise generally
made at a change of slope, occasioned by meeting with a different
soil.”
A Glossary of
Civil Engineering, Samuel Charles Brees (1841).
The Tunnel is probably better known
than would otherwise be the case through publication of the charming
watercolour of its southern portal under construction, by the artist
and civil engineer Samuel Brees (1810c.-65):

Northchurch Tunnel, September 1837.
A watercolour by S. C. Brees.
The contractor was W. & L.
Cubitt.
“At about the middle of it we pass
through the North Church Tunnel, the length of which is one fifth of
a mile. It has two handsome fronts of stone, with side walls
of brickwork, and is the same height and proportions as the Watford
Tunnel.”
The London and Birmingham Railway,
Roscoe and Lecount (1839).
Brees also reproduced the
specification and plans for the tunnel in the first edition of his
series of books on
Railway Practice, from which the following elevations are
taken:
|

An elevation from
Stephenson’s plans for the Northchurch Tunnel, reproduced in Railway Practice
by S. C. Brees (1838).
|
 |
|
Northchurch Tunnel
portal,
reproduced in
Railway Practice by S. C. Brees (1838). |
|
“This Tunnel is to consist of a
brick Arch, of the form shewn in the drawings, supported
by carved Side Walls, standing upon stone skew backs,
which are to be bedded upon the counter or Inverted
Arch, forming the base of the tunnel: this part is to be
one and a half brick in thickness, excepting the shaft,
as shewn on next drawing, and the arch and side walls
are to be two bricks thick throughout the whole length
of the tunnel, excepting for a length of 7 feet 3 inches
at the front, and at a distance of 12 feet on each side
of the shaft, together with the shaft length, where they
will be three bricks thick, or in such other places as
the Engineer may think it requisite to make them
thicker: in which latter case the Contractor shall be
paid for the increase according to the rate mentioned in
his Schedule of Prices. The Arch, if of the
thickness of one and a half brick, shall consist of
three half brick rings: if it be two bricks thick, it
shall consist of four and a half brick rings, and so on,
and each ring shall contain five courses of bricks more
than the ring immediately beneath it . . . .”
An
extract from Stephenson’s specification for Northchurch
Tunnel, from Railway Practice by S. C.
Brees (1838). |
The document went on to specify that
excavation was to proceed in what by then was the usual manner, of
sinking shafts at intervals along the tunnel’s alignment, from the
bottom of which a narrow heading was then excavated for the tunnel’s
full length before widening out commenced. The heading served
to prove the correct level and alignment, and help reveal any
unexpected hazards that had not been detected by trial boring:
“The Contractor must also sink two other
shafts on the centre line of the tunnel, one at each end of it, and
drive a Heading 4 feet wide and 5 feet high, the whole length of the
tunnel. This Heading must be carried through, before any part
of the main tunnel is commenced, and must be supported and kept open
during the execution of the whole work, by timbering or such other
means as may be deemed necessary by the Engineer . . . .”
An extract from
Stephenson’s specification for Northchurch Tunnel, from
Railway Practice by S. C. Brees (1838).
Although Northchurch Tunnel appears to
have posed no particular civil engineering challenges during its
construction, that does not mean that the excavation was free of
hazards for those who undertook the work. But in that era,
injury and loss of life in the workings was probably to be expected
at some stage during tunnel excavations:
“Frazer accordingly put in for, and obtained a
contract to carry a portion of the drift through Northchurch tunnel;
over this job he appointed George his gaffer, and George then got me
to be appointed his assistant and time-keeper. So to
Northchurch tunnel we went, early in October; and, under the
directions of the engineers, opened the drift at the north end of
the tunnel; sinking a shaft about midway on our length, which was, I
think, about one hundred and fifty yards. By the middle of
November we had six gang of navvies at work . . . . The soil through
which we were carrying the drift of Northchurch tunnel was of a most
treacherous character, and caused many disasters. Despite
every precaution, the earth would at times fall in, and that, too,
when and where we least expected. Thus, in the fifth week of
our contract, notwithstanding that our shoring was of extra strength
and well strutted, an immense mass of earth suddenly came down upon
us. This came from the tapping of a quicksand. One
stroke of a pick did it. The vein was shelving and the sand,
finding a vent, ran like so much water into the open drift; which
was of course speedily choked up. George Hatley was at once on
the spot; and, under his directions efforts were promptly made to
clear away the sand, so that the shoring should be re-strengthened
if possible before the earth above (deprived of the support afforded
by the sand) should collapse. The most strenuous efforts were
made in vain. There came a low rumbling, like the distant
booming of artillery, then followed crashes louder than the thunder,
startling us from our labour; and, while we were hurrying away, down
came the whole mass of earth, masonry, timber, and sand, crushing
five men under it.
Of these men three were dug out alive, and
removed — terribly mangled — to the West Herts Infirmary; the other
two were found dead.”
‘Navvies as they
used to be’, from Household Words, Vol. XIII., 19th January
1856.
This article is reproduced in full in the
Addenda.

Northchurch
Tunnel under construction, June 17th 1837, by John Cooke Bourne.
The original West Herts Infirmary was
founded by the eminent surgeon, Sir
Astley Paston Cooper, one of the Railway’s most implacable
opponents. [6] The hospital opened in
January 1827 for the “gratuitous relief of the necessitous poor”.
Construction of the London and Birmingham Railway inevitably added
to the hospital’s work, which by this time had moved from its small
beginnings to larger premises in Hemel Hempstead. The Railway
Company Directors donated £21 and the Contractors a further £25, but
they later arranged to pay 8s. a week for any workman admitted.
Delay in treatment ― especially for men excavating the Tring Cutting
― could result in death from loss of blood, and the Hospital staff
suggested that gangers should be shown how to apply a temporary
tourniquet.
On emerging from the Northchurch Tunnel, the line
continues its ascent through Dudswell to Tring where it reaches its
highest point at 419ft above sea level. Tring station also
marks the beginning of the 2½-mile cutting through the Tring Gap,
the excavation of which was undertaken by Thomas Townshend
(1771c.-1846), a successful contractor with experience of
large-scale earthworks on the Birmingham Canal, most notably the
huge cutting at Smethwick.
|
 |
|
Tring
Cutting, Grand Union Canal. |
Work on the Tring Cutting commenced in
September 1834. According to correspondence published in
The Mechanics’ Magazine, by the following year good progress had
being made:
“The work through Tring Hill is
proceeding very well, and, I may say, rapidly. A ‘temporary
bridge’ has been constructed across the canal at Seabrook, to carry
the earth over (the embankments being finished as far as there).
I understand it is not the intention of the Company to put up the
permanent bridge till all the earth shall have been carried over.
But the foundations for it have been put in some time. The top
is to be of iron. Mr. Townsend [sic.]
has lately been laying down a fresh set of rails (parallel
wrought-iron ones) in lieu of the common cast-iron, and a new set of
waggons have been put on the work. The temporary bridge over
the canal is something like a bridge when compared to that which was
put over the canal at Wolverton, and pulled down by the Canal
Company.
[7]
(By-the-bye, I think a vote of thanks ought to have been passed by
the Railroad Company and forwarded to the Canal Company, thanking
them for their unbounded kindness in destroying a bridge which must
have broken by its own weight, and occasioned, probably, a great
loss of life. By what I can learn, they get on very badly in
that quarter). Mr. Townsend will complete his part, before the
others are well begun. He keeps his men very steadily at
work.”
――――――――
“The excavation for
the London and Birmingham Railway, through Tring-hill, is proceeding
rapidly. Mr Townsend
[sic.] the
contractor has upwards of 500 men employed besides a great number of
horses. It is expected they will intercept the ‘Bulbourne
springs’ when they get deeper. These springs at present come
directly into the Grand Junction Canal. There is only one
fault to be found with the work in this neighbourhood, and that is
the steepness of the banks, they being only, for the excavations, in
the ratio of nine inches horizontal to one foot perpendicular.
In the event of a sharp frost, this ground, which is a sort of chalk
rag, will slake down like lime, and will consequently be a great
nuisance after the road is finished. The banks of the Grand
Junction Canal, in the deep cuttings collateral with the railroad,
are more than one to one, yet the slips which have occurred after a
sharp frost have been prodigious.”
From letters
published in The Mechanics’ Magazine, Volume 23, 1835.
The magazine’s second correspondent was
correct in his belief that the excavation would intercept the
Bulbourne Springs, as had been James Barnes’ experience some 40
years earlier when excavating the Grand Junction Canal cutting half
a mile to the west (See Chapter
VII., A Highway laid with Water). Robert
Stephenson was later to report that:
|
“The Tring cutting on the L and
B R/Way presents another forcible example of the
constant and rapid absorption of water by the chalk.
In the execution of that cutting a very large quantity
of water was encountered, notwithstanding the situation
was on the summit of the chalk ridge, forming the actual
brim of the basin, where it could not be supplied with
any water but such as fell upon the immediate
neighbourhood, yet it yielded upwards of one millions
gallons per day, and continues to yield an extraordinary
quantity up to this hour, without any sensible
diminution.”
Minutes of proceedings of the Institution of Civil
Engineers: Volume 90, Part 4. |
The
“large quantity of water” to which Stephenson refers is now
channelled from the railway cutting through a heading to enter the
canal summit.

The culvert
that drains the Tring Railway Cutting into the summit of The Grand
Union Canal. The flow of water shown here was after a period of
dry weather. The arch is about 4feet high.
During the drought of 1934, Edward
Bell, the canal company’s surveyor, reported that he was able to
walk through the dried out heading, but not wishing to retrace his
steps he emerged into the railway cutting ― he mentions, as he
climbed up the steep embankment, “feeling very scared as an
express train thundered along below”.

Tring Cutting
after the track had been widened during the 1870s to accommodate
four tracks.
“The Tring Excavation is about two miles and a
half long. The strata through which it was cut are composed of
the lower or grey chalk formation, without flints. It averages
forty feet, and for about one quarter of a mile is fifty-seven feet
in depth. Out of this hill were taken one million and a half
cubic yards of earth, which had to be lifted to the surface a height
of forty feet and then deposited in ‘spoil banks’. It was
executed by means of a number of ‘horse runs’ so called by
excavators from the men being drawn up planks nearly in a
perpendicular position by horses. A rope is attached to the
front of the barrow containing the soil, while the excavator takes
firm hold of the handles, and both barrow and man are drawn up the
plank, ― the latter having his body nearly horizontal during the
ascent. It is a fearful practice; and should any accident occur, by
the breaking of the rope or restiveness of the horse, the workman is
precipitated to the bottom in an instant.”
The London and
Birmingham Railway, Roscoe and Lecount (1839).

From a later era,
a horse-run in use on the Manchester Ship canal workings.
By February 1837, the Chairman was
able to report to the General Meeting that work on the Northchurch
Tunnel was complete, and the Board was optimistic that the line
would be opened to Tring by the Autumn. However, the heavy
rain during the winter of 1836-37, together with the influx of water
from the Bulbourne Springs, brought work in the cutting to a
standstill:
“The
quantity of water yielded by the cutting, in addition to that which
has fallen in rain, together with the argillaceous character of the
chalk in the Tring contract, rendered it absolutely necessary to
stop proceedings on the embankment, and to confine them to the
side-cutting and spoil. It is but justice, however, to the
contractor to add that he persevered in carrying on the embankment,
until the engineer reported that it became positively impassable.
Notwithstanding this temporary delay, the engineer is of opinion
that the completion of this contract will certainly not be much
protracted beyond October next.”
From the
Report to the 7th half-yearly General Meeting, February 1837.
In October 1837 ― apparently to the
surprise of all concerned ― Townshend relinquished his contract and
the Company took over the work:
“Another unpleasant affair for the Company
arose from the person who had the Tring contract becoming bankrupt ―
a matter least expected, perhaps, of any. He was a man of
capital and talent, and had established a reputation for years as an
able contractor. The works he had on his hands were of the
most extensive nature, and ought to have paid him well; when, to the
surprise of every one who knew him, he was suddenly declared to be
in difficulties through his contracts on the Grand Junction line,
and ultimately went into the [London]
Gazette, leaving his works at Tring, including the heavy cutting
through the chalk, to be finished as best it might.”
The
History of the Railway connecting London and Birmingham,
Peter Lecount (1839).
The reasons for Townshend’s bankruptcy
stemmed from difficulties over contracts he had with the Grand
Junction Railway Company coupled with a substantial increase in wage
rates, but within seven months he had paid off his creditors and was
able to return to contracting during his final years.
The
winter of 1837-38 was another of unusual severity, which delayed
work until the frost broke up. Stephenson was able to report
to the General Meeting held in February, that the Cutting was almost
complete and the next section of the line from the south would
shortly be opened:
“The Tring
Contract, which comprehended the most extensive excavation on the
line, is now nearly completed. The whole of the excavations
and embankments are ready for the further opening to Denbigh-hall,
except that about 4,000 yards of permanent road remain to be laid,
not in one length, but made up of several smaller portions.
There still remains work, which, as nearly as can be calculated,
must require three weeks to perform. The embankments
throughout this contract, consist almost entirely of chalk, which
being already well consolidated, and little liable to subsidence,
the immediate use of the permanent road may be reckoned upon as soon
as completed.”
From the
Report to the 9th half-yearly General Meeting, February 1838.
The line from Tring to Denbigh Hall
was opened to the public on the 9th April 1838.
|
CHAPTER 8
――――♦――――
|
FOOTNOTES. |
|
1. |
The clay is entirely free from
water, but its absorbing properties are such that when
it is exposed to air it swells out rapidly. |
|
2. |
A further viaduct to the west
of the main line was built to carry the former Watford
and Rickmansworth Railway (opened October 1862) over the
valley of the River Colne, between Bushey and Watford
High Street stations. |
|
3. |
The wedge-shaped stone blocks
used to line the facing curves of each arch. |
|
4. |
At its southern end, the
Colne embankment was formed of spoil excavated from the
Oxhey cutting, at the northern end with spoil from the
Watford cutting. |
|
5. |
Although in Aldbury parish,
Tring station lies at the northern end of this section. |
|
6. |
“I remember,” said Robert
Stephenson, describing the opposition, “that we called
one day on Sir Astley Cooper, the eminent surgeon, in
the hope of overcoming his aversion to the railway.
He was one of our most inveterate and influential
opponents. His country house at Berkhamsted
[Hemel Hempstead] was
situated near the intended line, which passed through
part of his property. We found a courtly,
fine-looking old gentleman, of very stately manners, who
received us kindly and heard all we had to say in favour
of the project. But he was quite inflexible in his
opposition to it. No deviation or improvement that
we could suggest had any effect in conciliating him. He
was opposed to railways generally, and to this in
particular. ‘Your scheme,’ said he, ‘is
preposterous in the extreme. It is of so
extravagant a character, as to be positively absurd.
Then look at the recklessness of your proceedings!
You are proposing to cut up our estates in all
directions for the purpose of making an unnecessary
road. Do you think for one moment of the
destruction of property involved by it? Why,
gentlemen, if this sort of thing be permitted to go on,
you will in a very few years destroy the noblesse!’
We left the honourable baronet without having produced
the slightest effect upon him, excepting perhaps, it
might be, increased exasperation against our scheme.
I could not help observing to my companions as we left
the house, ‘Well, it is really provoking to find one who
has been made a “Sir” for cutting that wen out of George
the Fourth’s neck, charging us with contemplating the
destruction of the noblesse, because we propose to
confer upon him the benefits of a railroad.’”
Lives of the Engineers ― George Stephenson and Robert
Stephenson, Samuel Smiles (1862). |
|
7. |
January 19th 1835: A company
[the London and Birmingham Railway Company]
were empowered by an act of Parliament to do all works
necessary and convenient for constructing a railway, and
among others to cross canals and make embankments in the
line; and in particular to cross a canal of which the
defendants [the Grand Junction Canal Company]
were the proprietors, and to make an embankment over a
valley near the same place.
Subsequent clauses in
the act restricted the company from doing any thing
which should obstruct the navigation of the canal, or
any part thereof; and specified the height and
dimensions of any bridge to be made and maintained for
carrying the railway over the canal.
The company,
for the purpose of transporting earth from the higher
lands on the south to the lower land on the north side
of the canal for constructing an embankment, erected a
temporary bridge over the canal, supported partly on
piles driven into the bed of the canal.
The defendants pulled down such bridge and thereby
destroyed the passage of communication for the carriage
of the earth.
Held, by the Master of the Rolls,
on a motion for an injunction to restrain the defendants
destroying any such bridge, or preventing such
communication, that the clause empowering the railway
company to cross canals in the progress of their works
was not restricted by the subsequent clauses which
applied to permanent bridges; and his Honor therefore
grained the defendants from obstructing the making or
use of such passage of communication.
Cases Relating to Railways and Canals: 1835-1840. |
|