THE GRAND JUNCTION CANAL
A HIGHWAY
LAID WITH
WATER.
THE CONSTRUCTION PROJECT
BACKGROUND
“The canals which intersect Middlesex are the Grand Junction
Canal, and the Paddington Canal. The former striking off from
the Thames at Old Brentford, passes the grounds at Sion Hill and
Osterley; and, running through a rich corn district near Hanwell,
Norwood, Harlington, West Drayton, Cowley, Uxbridge, and Harefield,
leaves this county near Rickmansworth. This canal, which is
navigable for vessels of sixty or seventy tons burthen, has fourteen
locks to Harefield Moor, where the level is 114 feet two inches
above that of the river Thames. From its numerous cuts, side
branches, and collateral streams, it is, beyond doubt, the most
important inland navigation in the kingdom, as it affords a direct
water communication to all the various manufacturing towns of
Warwickshire, Staffordshire, Lancashire, Derbyshire, and several
other counties. The general breadth of this canal is thirty
feet, but at the bridges it is contracted to fifteen. The
Paddington Canal branches off from it near Cranford, and is
continued on a level from thence to the dock at Paddington, the
sides of which are occupied with yards and warehouses, for the
reception and security of merchandise. The advantages derived
to the metropolis and the country at large from this canal are
likewise various and important. A third canal, called the
Regent’s Canal, stretching from the Thames, west of London, to join
that river near Limehouse, has been lately projected, and is now
carrying into execution.”
Encyclopaedia Londinensis,
Vol. XV. John Wilkes (1817)
Today, it is difficult to image the areas of Hanwell, Norwood and
Harlington, etc., being rich corn districts, or for that
matter Paddington Basin being occupied by yards and warehouses ― one
warehouse survives, although put to a different use ― but such was
the landscape through which the new canal passed and which it
served. Completed in 1805, until surpassed in 1887 by the
Manchester Ship Canal the Grand Junction was Britain’s most
expensive canal project. Originally estimated at £400,000, its
eventual cost was in the region of £1,500,000. [1]
Cost overruns are not unusual in complex construction projects.
In our own age the British Library, the Millennium Dome, the
Scottish Parliament, the Edinburgh Tramway and the Channel Tunnel
are examples of construction projects that have significantly
exceeded budget. Even the Manchester Ship Canal, at
£15,000,000, was almost three times over budget and two years late
in opening. Each of these projects attracted much concern
among its investors, as did the Grand Junction Canal.
This chapter draws mainly on contemporary sources to provide a feel
for the financial and engineering difficulties that beset this 18th
Century ― to use today’s terminology ― ‘transport
infrastructure project’.
――――♦――――
1792 ― QUESTIONS STILL TO RESOLVE
“It was in the year 1792 that this undertaking first had its
origin. In the beginning of that year the Marquis of
Buckingham instructed Mr. Barnes, the eminent engineer, to make a
survey of the country between Braunston, in Northamptonshire, the
place where the Oxford Canal has its junction with the present
canal, and the Thames near London, in order to mark out a line of
canal, whereby the circuitous course of the Thames Navigation from
Oxford might be avoided, and the transit of goods to the metropolis
accelerated.”
Navigable Rivers and Canals,
Joseph Priestley (1831)
When Barnes completed his survey in 1792, questions still to resolve
were the line that the Canal should follow south of Two Waters
(Hemel Hempstead) and the location of water sufficient to supply the
Tring summit. Some of the Grand Junction Canal Company’s
earliest published circulars address theses issues.
One of the first recorded shareholder meetings, [2]
convened by the Earls of Essex and Clarendon, took place at the
Essex Arms, Watford, on 20th October, 1792. The main business
of the meeting was to consider the plan of the Canal and decide
whether it should reach Southall through Watford and Harrow, or take
a longer but more favourable line along the Gade and Colne valleys
through Rickmansworth and Uxbridge. Having inspected both
routes, Jessop favoured the latter and supported by Barnes
recommended accordingly. The Rickmansworth route being
accepted, the meeting went on to vote in favour of a short branch to
link Watford to the main line, which, on account of their first
decision, now bypassed the town. On the following day the
Rickmansworth route was again approved, this time at a meeting
chaired by William Praed and held at the County Hall, Northampton.
Jessop reported to the Committee that there were many reasons for
preferring the Rickmansworth route. These are unrecorded, but
it is likely that a sufficiency of water was prominent among them.
Although water supply was an issue that affected the entire Canal,
supplying the Tring summit was to prove particularly challenging.
Writing in 1805, the civil engineer Thomas Telford, who had recently
inspected the Canal, referred to water supply in the introduction to
his report:
“. . . . the Line of Canal has unavoidably been carried over a
country, in many points of view unfavourable for Canal operations.
The line of the canal passes over and skirts along some of the
highest ground in the central parts of England . . . . this
circumstance has subjected the canal to the inconvenience of two
summits, and has rendered the supplies of water more difficult to be
procured than when canals are carried upon lower levels, or are
connected with more mountainous countries. . . .”
Supplying the Tring summit with water appears not to have been
investigated thoroughly at the outset, suggesting that the level of
traffic that built up following the Canal’s opening was greater than
anticipated. In his report to the Committee of 24th October
1792, Jessop expressed the opinion that the flow from Bulbourne
Spring together with that from the “Tale at New Mill” (Tring
Brook) would, between them, supply 30 lockfuls a day and that any
deficiency could be made up by steam pumping from a reservoir,
although none had then been planned; some ten years were to elapse
before the first of the Tring Reservoirs was opened at Wilstone. [3]
Another important water resource is the Wendover Stream; diverting
its abundant supply to the Tring summit appears not to have been
contemplated at this stage, for Jessop makes no mention of it and
neither is the supply channel (later to become the 6¾-mile Wendover
Arm) shown in the deposited plans.
In retrospect, Jessop’s opinion that “the practicality of getting
water sufficient is beyond doubt” proved over-optimistic, for
despite the resources that have been applied down the years to
flooding the Tring summit, water shortage has continued to pose a
problem. At the time of writing, the Tring summit was last closed
through water shortage in February and March 2012 ― this was
inconvenient, but during the Canal’s commercial heyday drought could
seriously hinder the passage of trade (and canal families’ piecework
income):
“Between Marsworth and Boxmoor, on the important canal which
connects London with Braunston and Leicester, there are 50 pairs of
barges waiting for water to float them through the locks. This
block is the worst effect of the drought in Hertfordshire and
Buckinghamshire. It is causing serious delays in the London
supply of all kinds of merchandise — coal and ironware from the
Midlands, new corn from some of the arable counties, condensed milk
from Aylesbury — and in the Midlands supply of sugar, tea and other
commodities in bulk from London. Heroic exertions on the part
of the Grand Junction company’s engineers and servants do not enable
more than 80 to 90 barges a week to pass over Tring Summit, whereas
in times of plentiful water 130 pass.”
Bucks Herald, 11th
October, 1902.
Telford also identified in his survey a number of sections where the
water that had been procured was being wasted through leakage.
One example that he gave was to the south of the Tring summit:
“it will be chiefly in the upper part of the line in this
district, that is, between Cow Roast and Box Moor, that much
attention and expense will be required, in order to prevent
leakage.”
In fact it was along the section of the Canal to the south of
Boxmoor where leakage was later to bring the Company into conflict
with the local water millers, a conflict in which Telford was to
become involved.
――――♦――――
1793 – WORK COMMENCES
Following the passage of the first Grand Junction Canal Act (30th
April, 1793), construction began promptly. By December of that
year the Committee was able to report that “the works on the
Grand Junction Canal are proceeding with an astonishing rapidity,
and the number of men now daily employed amounts to 3,500”.
However, their report goes on to say that expenditure was greater
than anticipated and it reminded subscribers to settle promptly the
calls on their partly paid shares. This was an early
indication of the cost overruns that were to affect the project and
that required recourse to Parliament on several occasions for
authority to raise additional capital. Jessop had already
informed the Committee that his construction estimate included an
allowance for the inflationary pressure on wages from competing
canal projects (this was the period of canal mania):
“I have thought it necessary to make very large allowances for
the increase and increasing price of labour, in consequence of the
numerous works of this kind now in agitation, and I have full
confidence that the expense will not exceed the estimate.”
Report to the Committee,
24th October, 1792 – William Jessop
But what Jessop could not have allowed for was the additional
inflationary pressure of the French Wars (1793-1815) together with
the cost of function creep [4] that so often
affects major projects. He did, however, inform the
Committee that even if the project was completed at twice his
estimated cost, it would still be worth doing.
――――♦――――
1794 – WORK PROGRESSES
By May 1794, Jessop was able to report good overall progress.
The canal from Brentford to Uxbridge was almost complete and he
expected it to open by late September, although shortage of
labourers [5] during harvest-time was a problem,
which probably accounts for this section being opened (with the
usual celebrations) rather later than Jessop had estimated:
“That part of the Grand Junction Canal from the river Thames,
near Brentford, to the town of Uxbridge, was opened on the 3rd
instant, for coals, and all sorts of merchandize to be navigated
thereon; comprising upwards of twelve miles of this great
undertaking. The opening of this part of the Canal was
celebrated by a variety of mercantile persons of Brentford,
Uxbridge, and Rickmansworth, and their vicinities, forming a large
party, attended by a band of music, with flags and streamers, and
several pieces of cannon, in a pleasure-boat belonging to the
Corporation of the city of London, preceding several Barges laden
with Timber, Coals, and other merchandize, to Uxbridge. After
which the party dined at the White Horse Inn.”
Northampton Mercury,
15th November, 1794
Work was also progressing on the northerly of the Canal’s two
summits at Braunston. The Braunston summit was one of the
early points of attack, work commencing there in May of the previous
year:
“One part of the Braunston canal, which is to form the Grand
Junction, was begun last week with great spirit. Three hundred
and seventy men were paid on Saturday night, and more hands are
arriving every day. Another part will shortly be set about by
Mr. Clifton, with his new machine for saving three fourths of manual
labour, in cutting and removing earth, &c.”
Northampton Mercury, 25th May, 1793
It is doubtful if Mr. Clifton’s “new machine” was a success,
for there is no further mention of it.
The summit level is just over 3 miles long (comparable to that at
Tring), 2,042 yards of which passes through the Braunston tunnel,
which Telford later described as “being in a tolerably straight
direction”, a reference to the slight S-bend in its alignment.
Because the ground in the vicinity was impervious clay rather than
absorbent chalk, water supply was not to be the challenge that it
was at the Tring summit.
The 1793 Act also authorised the construction of a 1½-mile branch
from the summit to Daventry. Jessop estimated that it would
require eight locks to cope with the 52 feet difference in levels
and cost £6,000 to build, but he could offer no opinion as to the
branch’s commercial viability. Because of its falling
gradient from the town, the Daventry branch would have supplied the
summit with water, but although its position is shown in the Canal’s
deposited plans it was not built. [6]
Instead, the Braunston summit is supplied with water by what Telford
later described as “small rills on the Braunston side of the
summit” and by a feeder channel from Watford Park, which joins
the summit near Welton. These feeders worked in conjunction
with a small reservoir (which no longer exists) near the northern
end of Braunston Tunnel and the much larger Drayton Reservoir,
opened in 1796, which lies to the north west of Daventry.
In his report, Jessop expressed reservations about the quality of
the bricks being made for Braunston Tunnel [7] and
the quantity; “as is commonly the case at the outset of
brick-making, they [the brick-makers] want flogging to their
duty”. A section of canal to the east of the tunnel had
been flooded and was being used to transport bricks. Work on
the cuttings was progressing well, as were the high embankments at
Weedon, Heyford and Bugbrook (the great embankment between Wolverton
and Cosgrove was a late addition to the original plan). Work
had also begun on the Blisworth Tunnel, but too little had been done
to give any indication of the setbacks yet to come. The
Wendover Arm was by now seven-eights complete (so was probably
complete by the end of 1794); here, Jessop draws attention to the “very
leaky” terrain over which it was being built, a portent for the
future.
Jessop also refers to progress on the Tring cutting (“The Deep
Cutting at Marsworth”), where the ground along the line had been
cut to an average depth of five feet, sufficient to make Jessop
hopeful
“that this heavy piece of work will be executed at an expense
considerable less than was first expected” ― it was not to be.
 |
Tring
Cutting, looking north from Marshcroft Lane bridge (No.
134).
|
――――♦――――
1795 – PROJECT CONCERNS
By August, 1795, the Committee was becoming concerned about
escalating costs. To date, the value of work on the Canal
amounted to £296,000 and Jessop estimated that a further £312,000
was needed to complete construction, of which monies owing and
assets in hand amounted to £177,000, leaving a deficit of £135,000.
In explaining the position to their shareholders, the Committee
pointed to a number of unforeseen expenses, some of which had been
imposed by Parliament, such as a change in the method by which the
canal banks were formed (£17,000) and an additional duty on bricks
(£7,200). Other items included the purchase of water mills (to
obtain their water rights, £10,500), construction of reservoirs
(£7,000) and an alteration to the line of the Canal to pass through
Cassiobury and Grove Parks (£9,000), this being offset by Parliament
authorising an additional levy of two-pence per ton “for and in
consideration of the more constant, speedy, and safe communication
proposed by the said deviation”. [8] The
Cassiobury/Grove Park deviation brought the Canal closer to Watford
― to which a branch was then planned ― and despite the high cost of
the land, it probably cost little more to build than the original
route, which would have required an aqueduct across the Bulbourne
and a tunnel at Langleybury.
In addition to the financial impacts of changes and additions to
specification and the inflationary pressures of the age, land was
also proving more expensive than anticipated:
“The price of materials, the expense of carriage and provender
for horses, have been much enhanced; and the dearness of provisions
has greatly enhanced the price of labour. And the price which
hath been paid for the land purchased (in general) much higher than
the same had been calculated upon. Before beginning the work,
Mr Jessop found it advisable to make the locks something larger than
they were first intended, and to make the tunnels something wider
and higher; the canal has also been made five feet in depth, instead
of four feet six inches, as computed in the original estimate.”
GJCC Statement of
Expenditure, 6th August, 1795
A further expense to find its way into the report was “the
payment of interest to Proprietors out of capital stock”.
During this stage of the Canal’s construction, shareholder received
5% p.a. interest payable on the nominal value of their shareholding,
with interest payments being funded mostly from capital due to the
Canal’s very limited earnings at this stage. The Company
projected that between midsummer 1794 and March 1798, interest
payments to subscribers, if continued, would account for £75,000 and
that suspending them was “a measure highly expedient”.
In the event, the Committee decided to credit subscribers’ accounts
with the interest owing, but to suspend payment until directed by a
future General Meeting.
And so began the process of finding ways and means of financing the
Canal’s construction, which were to continue for the remainder of
the project. This involved containing costs ― even Jessop’s
role as Chief Engineer was eventually dispensed with (ostensibly) as
a cost-cutting measure ― increasing tolls, raising further capital
by selling shares, and raising loans, much of which required the
authority of further Acts of Parliament. These measures
commenced later that year with an application to Parliament to raise
a further £225,000 of share capital. [9]
――――♦――――
1797 – ESCALATING COSTS
 |
Northampton
Mercury, 5th June, 1796. |
Every major construction project has its
critics and that to build the Grand Junction Canal was no exception.
In 1797, a long pamphlet appeared entitled “Observations on the
present state of the Grand Junction Canal, submitted to the
Attention and Consideration of the Proprietors”. In it,
numerous allegations were laid against the Committee implying
mismanagement and incompetence. The author cited, as evidence,
the heavy overspend on budget, money wasted on wharfs and tunnels
(most notably on the Blisworth Tunnel, which was by then in limbo)
and the heavy expense of building the Tring cutting. Overall,
the pamphleteer considered the Committee to be “inert and
inexperienced”, pointing to declining investor confidence and
the fall in share price from a £90 premium to £30 to support that
view. To make the best of a bad job, the writer recommended
that the Canal’s “upper [southern] end ought to stop, and
the lower end prosecuted as far as the inland coal trade would
extend”.
The pamphleteer’s allegations probably contained sufficient germs of
truth to encourage the Committee to mount a vigorous defence.
At the General Assembly held on 7th November 1797, it was resolved
to publish a rebuttal of the main allegations, preceding which the
Committee assured their shareholders that they had “conducted the
affairs of this Company with the strictest zeal and integrity”.
In their response, the Committee gave credence to the charge that
costs were continuing to exceed budget. Again, they were at
pains to attribute overruns to additions to their original plan
(some of which had been heard before), such as the need for the
Aldenham Reservoir, [10] for aqueducts across the
Colne and a change in the line at Harlington, while other unexpected
costs stemmed from additional linings for the Canal, clearing the
Braunston Tunnel workings of quicksand “which from the borings
there was no reason to expect”, and “widening and deepening
the canal beyond the original design, and the consequent increase of
expense in the width of every bridge”. [11]
The inflationary pressures of the French Wars were also beginning to
bite, with military needs competing for scarce manpower and
manufacturing resources. As the Company explained, procurement
was being affected by “the difference of the War price for all
labour and materials, when compared with the sums estimated for them
in profound peace”. But on the bright side, the Committee
report that work on the Tring cutting and on short sections to the
north and south of it were nearing completion, and that even in its
unfinished state the Canal would soon generate revenue estimated at
£20,000 p.a.
A section of the Committee’s response also provides an interesting
explanation of the sequence in which the various sections of the
Canal were built. In addition to the commercial considerations
―
i.e. what sections were likely to generate the most revenue
soonest ― there was the perennial problem of water supply to
contend with, for an insufficiently flooded canal is near to, or
completely useless. In explaining why work on the section
south of Blisworth tunnel should not yet go ahead, the Committee
pointed out that not only were twelve locks required to take the
Canal down to Cosgrove, but until the Blisworth tunnel was completed
there would be insufficient water to flood them. A section
near Stony Stratford, about five miles in length, could have been
completed but there was no commercial sense in so doing, while the
section from Cosgrove up to Fenny Stratford could not be flooded
until it had been reached by the Canal bringing water down from
Tring.
――――♦――――
BARNES REPORTS ON PROGRESS
The Committee supplemented their rebuttal of the mischievous
pamphlet with a report [12] from Barnes on the
present state of construction. This is revealing. To the
south, the Canal was now open to Kings Langley and would shortly
reach Two Waters (Hemel Hempstead), but Barnes then moves on to
reflect on “the great difficulties, delays and impediments”
to construction being caused by “the immense quantity of water
springing from the earth at the locks”, while the porous ground
over which the Canal was being built in the vicinity of the Nash and
Apsley paper mills required it to be lined. In later years,
leakage along this section was to result not only in the Company
paying heavy damages to the paper manufacturer John Dickinson, whose
water mills had suffered in consequence, but in an alteration to the
route followed by the main line. North of Two Waters, work had
begun cutting the section up to the Tring summit and much building
material (bricks and timber) had been deposited along the route in
readiness. Barnes was optimistic that the ground over which
this section was to pass would prove favourable.
Work had commenced at the outset on the Tring summit due to the
heavy excavation required, about half of its 3-mile length being in
a cutting some 30ft deep in places. Although the Wendover Arm
seems not to have featured in the original planning (1792), its
importance in diverting the Wendover Stream 6¾-miles along the 394ft
contour to the Tring summit must soon have been recognised.
The Arm was probably complete by the end of 1794, but in any event
well before the southern section of the Canal reached the Tring
summit early in 1799.
In his report, Barnes informed the Committee that work excavating
the Tring cutting was progressing well, but two problems had been
encountered. A section of about 500yds was found to be
extremely waterlogged, causing slippages in the adjacent walls of
the cutting. These required drainage headings to be driven
into the banks behind the slips to lead off what Barnes describes as
“a great quantity of water”. Further south along the
summit, a section of the Canal passed over ground that was found to
contain gravel and was porous. This Barnes planned to deal
with using the earth from the slips, which was found to be suitable
for lining and which, he says,
“I intend taking away with barges”, implying that by this
date part of the summit was already flooded.
At the northern end of the summit, the deposited plans show a rather
different route was intended from that eventually taken. The
Canal plan and section show the summit pound continuing northwards
along the contour from a location in the vicinity of Marsworth top
lock (No. 45) to a point about ¼-mile to the north of Lower Icknield
Way. From here, the Canal was to descend via a closely spaced
flight of ten locks [13] to the east of Marsworth
Parish Church to join the present route. However, the Canal as
constructed follows a line to the west of Marsworth Parish Church,
descending the incline from Bulbourne along the course of the
northern outflow of Bulbourne Head (or Bulbourne Water) via the
flight of seven locks seen today. The Tring summit pound is
thus about ½-mile shorter than originally planned, but why this
change was made is unknown.

Section and plan showing the
variation in the course of the Tring summit at its
northern end.
The Canal, as built, passes to the west of
Marsworth Parish Church, not to the east as shown, commencing its
descent from the summit well to the south of Lower
Icknield Way. |

North of the Tring summit, Barnes believed the ground to be “upon
trial, exceedingly favourable”
stating that he expected the cost of the Canal per mile would be
comparable to that of the section between Uxbridge and Two Waters.
Work had already begun in the vicinity of Marsworth and Cheddington,
where Barnes reported finding plenty of good clay for brick-making,
and he was optimistic that the section to Fenny Stratford would be
completed at the same time as the Tring summit was reached from the
south. He then moves on to report progress on the problematic
Blisworth Tunnel.
The Blisworth tunnel was recognised to be one of Grand Junction
Canal’s three major engineering challenges, [14]
construction having commenced in 1793. Trial boring along the
line of the tunnel from the hill above failed to reveal that the
strata through which the tunnel was to pass dipped in the centre.
The effect of this was to cause the horizontal tunnel to move out of
a layer of impermeable clay and into one of porous, unstable rock
which, together with the layer of impermeable clay beneath it,
formed a subterranean reservoir.
By the end of 1795 the tunnel had moved into this water-bearing
stratum, resulting in such severe flooding in the workings that
excavation came to a virtual standstill. The Committee was
then faced with the decision of whether to restart the tunnel on a
different alignment, the option favoured by Barnes, or take the
Canal over Blisworth Hill using a system of locks, reservoirs and
steam pumping, the solution favoured by Jessop. Faced with
their professional advisors’ conflicting views, the eminent civil
engineers John Rennie Snr. and Robert Whitworth were engaged to
assess the situation and give an opinion. Following inspection
and deliberation the pair decided in favour of the tunnel and the
Committee ruled accordingly, placing Barnes ― who must already have
been carrying a considerable burden of other responsibilities ― in
direct control of the works.
In an age when large-scale tunnelling was in its infancy, Jessop’s
recommendation was undoubtedly the safer, although it would have
brought its own costs and problems. Locking over Blisworth
Hill would have caused a significant delay to traffic added to which
would be difficulty in ensuring a sufficient water supply at the
summit; there was also the cost of operating and maintaining the
locks and pumping system. On the other hand the tunnel has
been much affected down the years by distortions caused by movement
in the interface between the clay and oolite layers, which has led
on several occasions (most recently in the late 1970s and early
1980s) to closure while expensive repairs and rebuilding was carried
out.
By November 1797, the tunnel’s workforce had been deployed to more
important construction further south, work being continued, at
Barnes’s insistence, by a skeleton team who continued to drive
headings into the hill to carry off the large amount of subterranean
water (a pilot heading later became the standard tunnelling
technique). Barnes reports that this essential work was
proceeding, and he recommends that full-scale activities recommence
by the following spring in order that the tunnel “may be
completed without loss of any time”.
――――♦――――
1798 – FURTHER PROBLEMS AT THE TRING SUMMIT
By June 1798, the advancing Canal had reached Berkhamsted from where
Barnes submitted a further report. In it he informed the
General Assembly that by the end of September he expected the Canal
to be navigable from Brentford to Wendover. He then returned
to a problem described in his previous report, “that the deep
cutting at Tring summit hath occasioned a great additional expense,
by the various slips that have unfortunately happened” and he
goes on to describe “the bottom of the Canal is in many instances
so soft, that a staff may be run down eight or ten feet
perpendicular below the bottom level of the canal with great ease”.
The condition of the ground through which the cutting was being
driven was probably due, in part, to it passing along the course (as
it then was) of the River Bulbourne, and partly to cutting into the
aquifer from which rose some of the springs in the locality, the
Bulbourne Springs and Clarke’s Spring being close to the line of the
Canal.
When Barnes undertook his survey of the Braunston to Brentford
route, he was faced with the problem of how best to take the Canal
over the barrier imposed by the Chiltern Hills. This 47-mile
chalk escarpment extends north-eastward from the Wiltshire Downs and
the River Thames towards the Dunstable Downs and Luton; skirting
around it was not an option. Of the slight depressions in the
ridge, Barnes chose to take the Canal through the Tring Gap.
The problem was then to obtain sufficient water to supply the summit
level and the declining gradients to the north and south.
The water resources in the immediate vicinity of Tring comprised,
principally, four springs, at Miswell, Frogmore, Dundale and
Bulbourne Head. The outflows from Miswell and Frogmore powered
a watermill at Gamnel, which the Company bought, diverting its
millstream (the Tring Brook) into the Wendover Arm. It is
unclear how the Dundale outflow was treated, but today it flows
underneath the Wendover Arm into Tringford Reservoir. As for
Bulbourne Head:
“About two miles from Ivinghoe is a place called Bulbourne,
belonging to John Sear, Esq. of Tring Grove. Here is said to
be the original source of the river Thames: there are two springs,
which divide within ten yards of each other, one running due east
and the other west. [15] Mr. Sear has made
a fine canal for a pleasure-boat, one mile in length.”
Topography of Great Britain,
George Alexander Cooke (pub. 1817)
At this date, the two springs ― known together as Bulbourne Head or
Bulbourne Water ― formed a considerable lake and the source of the
River Bulbourne, which today rises several miles to the south in the
vicinity of Dudswell. The deposited plans show “Bulbourne
Water, purchased of Mrs Mary Seare” [16] to
lie along the Canal’s summit route near the present day hamlet of
Bulbourne. The 1793 Act gave the Company authority to purchase
part of Mary Sear’s “plantation”, [17]
providing that the Company built a dam, fitted with a sluice, which
the lady could use to discharge water into the Canal or hold it
back, which suggests that she made use of the “Bulbourne Water”,
perhaps as Cooke seems to think, for leisure purposes. A
further provision in the Act also forbade the Company “to erect
any lock within the distance of One Mile on either side of the
Bulbourne Head aforesaid, without the consent of Mary Sear . . .”
but the reason for this provision (and others like it elsewhere in
the Grand Junction Canal Acts) are lost in time. It might,
however, explain why the original plan was to descend from the
northern end of the summit from a point on Lower Icknield Way to the
east of Marsworth Parish Church, rather than from Bulbourne
Junction.
Today, the dried-out depression once occupied by Bulbourne Water is
plainly visible in satellite mapping, with the Canal crossing its
western end. The reason that Bulbourne Water is now dry stems
from the draining effect of the Canal cutting on one side, and of
the London & Birmingham Railway cutting (constructed some 40 years
later) on the other. It appears that during the construction
of the railway cutting, it was anticipated that the feed to
Bulbourne Water would be intercepted . . . .
“The
excavation for the London and Birmingham Railway, through
Tring-hill, is proceeding rapidly. Mr Townsend the contractor
has upwards of 500 men employed besides a great number of horses.
It is expected they will intercept the
‘Bulbourne
springs’
when they get deeper. These springs at present come directly
into the Grand Junction Canal. There is only one fault to be
found with the work in this neighbourhood, and that is the steepness
of the banks, they being only, for the excavations, in the ratio of
nine inches horizontal to one foot perpendicular. In the event
of a sharp frost, this ground, which is a sort of chalk rag, will
slake down like lime, and will consequently be a great nuisance
after the road is finished. The banks of the Grand Junction
Canal, in the deep cuttings collateral with the railroad, are more
than one to one, yet the slips which have occurred after a sharp
frost have been prodigious.”
The Mechanics' Magazine,
Volume 23, 1835
. . . . and such was the case. Robert Stephenson, the
railway’s civil engineer, was later to report:
“. . . . The Tring cutting on the L and B R/Way presents another
forcible example of the constant and rapid absorption of water by
the chalk. In the execution of that cutting a very large
quantity of water was encountered, notwithstanding the situation was
on the summit of the chalk ridge, forming the actual brim of the
basin, where it could not be supplied with any water but such as
fell upon the immediate neighbourhood, yet it yielded upwards of one
millions gallons per day, and continues to yield an extraordinary
quantity up to this hour, without any sensible diminution.”
Minutes of proceedings of the
Institution of Civil Engineers: Volume 90, Part 4
Like Barnes before him, Stephenson had cut into the aquifer that fed
the Bulbourne Springs. The
“large quantity of water” to which he refers is now
channelled from the railway cutting through a heading to enter the
canal summit to the south of Marshcroft Lane Bridge. During
the drought of 1934, Edward Bell, the Company’s section inspector,
reported that he was able to walk through the dried out heading, but
not wishing to retrace his steps he emerged into the railway
cutting. In his memoir he mentions, as he climbed up the steep
embankment, “feeling very scared as an express train thundered
along below”.
And so the Tring cutting was driven through waterlogged ground, with
its walls slipping in places. In his report, Barnes again
explains the technique of driving headings into the cutting walls to
carry off the water, but he now describes a further technique, that
of
“piling, stretching and campshooting” (sic.) with the canal bed
being “planked very close”. Following World War I, the
banks along Tring summit were strengthened to protect against
erosion. In his memoir, Edward Bell recalls that:
“. . . . considerable difficulty was experienced in the Tring
Summit because halved tree trunks had been laid in the bed of the
canal across the waterway at intervals with timber piles at each end
of the tree to prevent the toe of the high offside bank from
encroaching into the waterway.”
Memoirs of a British Waterways Canal Engineer,
Edward Bell
No doubt Bell had encountered Barnes’s piling, stretching,
campshooting and planking.
――――♦――――
1798 – WORK PROGRESSING, COSTS ESCALATING
By June 1798, between two and three miles of canal had been
completed north of the Tring summit, about one million bricks had
been made and a team of nine moulders were at work making more.
Barnes recommended to the Committee that the cutting northward
should proceed swiftly to meet with “the Great Chester Road”
at Fenny Stratford, thereby capturing the road transport to London
and increasing the Company’s toll revenue accordingly. This
would then free up manpower resources to enable “a strict
attendance to the execution of the [Blisworth] tunnel”,
which Barnes believed could be completed in two years “or
thereabouts; then, if the tunnel should not be early proceeded upon,
the want thereof will be so great an impediment to the navigation,
that the delay will hereafter be very much lamented”; in that
assessment he was undoubtedly correct, although the impediment would
be mitigated to an extent by Jessop and Outram’s horse-drawn railway
over Blisworth Hill.
Barnes’s report (2nd June, 1798) was accompanied by a summary of the
Company’s cash account at 1st May, 1798:
Receipts |
… … … … … … … … … … … |
|
£620,687 |
|
Payments: |
|
|
|
|
|
Purchase of land, salaries,
etc |
£143,458 |
|
|
|
Payment of interest to
subscribers |
£40,061 |
|
|
|
Building cost of 47 miles of
Canal |
|
|
|
|
Reservoirs, Feeders, etc. +
WIP |
£429,687 |
£613,206 |
|
|
Balance |
|
|
£7,481 |
|
Monies owing |
|
|
£43,226 |
|
|
|
|
|
|
Funds available |
|
|
£50,707 |
That only half of the 93½-miles of canal had been opened by this
date was a clear indication that the funds then available were
insufficient to complete the project and that further capital was
needed. And so the Committee announced their intention to
raise £150,000 of 5% loan stock, convertible to shares by 25th
March, 1803 (most of it was). But the under-estimation of
construction costs continued, the outcome being that in later years
the Committee were to return to their shareholders for further
capital in one form or another until by June, 1804, the Company’s
capital account exceeded £1.3M. Against this background, it
becomes easier to understand why the construction of some of the
planned branch canals were delayed or not proceeded with.
In the meantime, the continual haemorrhaging of capital through the
5% p.a. interest payments on subscribers’ shareholdings, ceased.
This decision was taken at the General Meeting held on 6th November
1798, by which time the cumulative interest already paid exceeded
£40,000. At this meeting it was decided to convert the
interest due for the 12 months ending midsummer 1798 into “a
Mortgage or Assignment of the tolls of the said Navigation”, at
5% p.a. interest (a further loan), and that following midsummer
1798, shareholders would instead receive dividends to be paid out of
toll revenue after deductions had been made to cover operating
expenses.
Since the first sections of the Canal had been opened for business,
[18] toll revenue had been rising gradually,
assisted by Parliament’s approval of additions and increases to the
toll rates laid down in the 1793 Act. The Act of 1805 [19]
granted the Company further relief by lifting another provision of
the 1793 Act, that which permitted toll-free use of the Canal by the
armed forces. Before the coming of public railways, there are
numerous newspaper reports of the Grand Junction Canal being used
for military transportation, undoubtedly added to by the needs of
the French Wars. Lifting this exemption would have provided a
useful boost to revenue.
――――♦――――
1799 – THE OUSE VALLEY AND BLISWORTH HILL
By June 1799, the Committee was able to report that they had
inspected 64 miles of completed Canal, which despite the severe
winter just passed they found to be in satisfactory condition.
Barnes was also able to report (probably in May 1799) that work on
the section between the Tring summit and Fenny Stratford was
progressing “very rapidly” and he remained optimistic that
the terrain onwards to the temporary terminus to be set up to the
south of Stoke Bruerne “appears so very favourable for execution”.
Furthermore, the problem of water supply would there be met by the
drainage water issuing from the Blisworth Tunnel workings, which
together with other sources was judged ample “to supply the locks
equal to any trade that can be expected to arise”.
The major obstacle between Fenny Stratford and Cosgrove was the
valley of the Great Ouse, which lies across the line of the Canal
and is the lowest point between the summits at Tring and Braunston.
The Canal was originally planned to descend into the river valley
via a flight of four locks and to ascend the opposite side by a
further four lock flight. Locking into and out of the river
valley would have delayed traffic added to which, because the river
was to be crossed on the level, there was the potential for serious
disruption when it was in flood, which occurred from time-to-time.
The locks on the southern side of the valley would also have
increased the demand for water from the Tring summit where it was
often at a premium, this lockage water being lost into the Great
Ouse.

An artist’s
impression of the Cosgrove Embankment under
construction, showing Jessop’s aqueduct and the original
scheme for crossing the valley. |
In 1799, Barnes suggested to the Committee that, as an alternative,
the Ouse valley might be crossed by a high embankment in which a
section would contain an aqueduct to carry the Canal over the river.
This would avoid the problems inherent in the planned system of
locks, but such a substantial earthwork ― approaching a mile in
length ― would take about two years to build. The Committee
decided in favour of the embankment and aqueduct, but to avoid delay
to the opening of the final section of canal (Fenny Stratford to
Stoke Bruerne) while they were being built, they decided to press
ahead with the construction of the two planned flights of locks, but
to build them as temporary structures. [20]
They were completed in September, 1800.
The progress now being made towards Cosgrove laid bare the obstacle
of Blisworth Hill. Other than excavating the drainage
headings, work on the tunnel had been dormant since March 1797 when
the original alignment had been abandoned. It was now apparent
that the new tunnel would not be complete in time to meet the main
section of the canal then advancing rapidly from the south.
Writing in 1797, William Pitt described the problem that the
Committee faced:
“The trade of this canal makes a stop at Blisworth at present;
very considerable difficulties having arisen in the execution of a
tunnel, or excavation, of about two miles in length, under the high
ground at Blisworth: the difficulties arise from the under stratum,
on a line of the tunnel, which consists of a calcareous [21]
blue marl, extremely friable on exposure to air or moisture; and,
the springs being powerful, the water, on coming in contact,
converts this marl into liquid mud, which has occasioned the blowing
of the shafts and sheeting of the tunnel; and some time must elapse
before it can be finished and rendered navigable.”
The Agriculture of the
County of Northampton, William Pitt (1797)
As arrangements currently stood, it was realised that Blisworth Hill
would impose an increasing barrier to commerce, particularly in
shipping the southbound cargoes of coal that were building up at the
‘port’ of Blisworth:
“Pit-coal from the Staffordshire collieries, is now brought
plentifully to Blisworth, by the Grand Junction canal . . . . At
Blisworth are erected extensive wharfage and warehouses for goods,
two new inns on the canal banks, and there are five or six thousand
tons of coal in stacks on the wharfs; a large number of canal boats
and trading boats in the port, and two new ones on the stocks,
building. A considerable hurry and bustle of business is
created here by this canal.”
The Agriculture of the County of Northampton,
William Pitt (1797)
Apart from coal, toll records show that among the other bulk
commodities that were now being shipped by canal were stone, timber,
pig-iron, salt, bricks and slate ― indeed, in the years that
followed the Canal’s opening, traditional thatched roof coverings in
its locality were gradually replaced with slate. The build-up
of goods at the transhipment wharfs on either side of Blisworth Hill
was such that the existing road [22] between them
was considered inadequate to cope with the increasingly heavy flow
of traffic. To this end, Jessop investigated the feasibility
and economics of constructing a double-track horse-tramway. In
his
report of April, 1799
(counter-signed by Barnes), he submitted a detailed argument in
favour of a rail link to run from Blisworth “to the crossing of
the Towcester River”, [23] a distance of some
3¼-miles at an estimated cost of £24,000. The Committee
endorsed the plan, informing the shareholders that compared with
road transport the facility of an “iron road” was “beyond
calculation”. [24]
 |
The Little Eaton
Gangway, an example of a
horse-drawn
tramway. |
Benjamin Outram (1764-1805), canal
engineer and the leading practitioner of early railways, [25]
was contracted to construct the line. The form of track that
he used was L-shaped cast iron plates fastened to stone sleepers
with oak pegs, the sleepers being laid on a bed of gravel and small
stones. No record of the line’s gauge has survived, but it is
thought to have been 4ft 2ins, a gauge favoured by Outram for other
of his railway projects. The rail wagons were fitted with flat
rather than the flanged tyres used by later rail vehicles; these
were guided by the uprights of the L-shaped plates, the plates’
horizontal sections supporting the wagon’s weight. Flat tyres
also permitted the wagons to be run off the rails at either end of
the line and hauled across the wharfs where ― at least in the cases
of coal for nearby Buckingham ― they were hoisted into a narrow
boat. The tramway appears to have been in operation by June of
1800, for Company advertising of that date refers to “. . . . a
temporary cast-iron rail road has been adopted, until the tunnel and
locks could be completed . . . .”
Earlier that year, the Canal had reached Fenny Stratford where the
usual ceremonial opening took place to mark the occasion:
“The Grand Junction Canal was on Wednesday opened for barges from
the Thames at Brentford, to Fenny Stratford, in Buckinghamshire, and
early in the morning a number of boats departed from Tring, in
Hertfordshire, at which place the canal has been completed these two
years past; about one o’clock they passed through Leighton, in
Bedfordshire; and a short distance before they reached Fenny
Stratford the Marquis of Buckingham, accompanied by a number of
friends and principal proprietors, attended by the band and a party
of the Buckinghamshire Militia, met them. — They then went in grand
procession to Fenny Stratford, where they were received with firing
of canon belonging to the town and other demonstrations of joy.
The Marquis and the proprietors retired to the Bell Inn to dinner”.
Jackson’s Oxford Journal,
31st May, 1800
――――♦――――
1800 – BLISWORTH TUNNEL
Work had now commenced cutting from the River Tove towards Cosgrove
to meet the Canal advancing from the south. When exactly the
two sections met is unclear; the respected canal writer John
Priestly gives only the year, 1800, [26] but other
known dates suggest that, if this was so, it was late in the year.
By the following June, the Company was advertising the canal to be
complete from Brentford to Braunston, with conveyance over Blisworth
Hill by way of an “iron railway”. It is unclear whether
this advertising was purely to drum up trade, or an indication that
the Canal did not open for business immediately.
During the summer of 1800, advertisements appeared in the press
inviting the public to subscribe to a £100,000 5% convertible loan,
its principal stated purpose being to fund completion of the
Blisworth tunnel. [27] Since work on the
tunnel had been abandoned in March 1797, the only activity had been
to drive a narrow brick-lined heading beneath the alignment of the
future tunnel to drain the water that had led to the original
workings being abandoned. With the Canal now complete in other
respects, attention was turned to the tunnel’s excavation.
Plans for the tunnel [28] were drawn up by Jessop
and the work put out to tender. The successful bidder was a
consortium, whose rate was £15 13s. per yard, payments to be made
against completion certificates authorised by Barnes.
Twenty-one shafts (pits) are known to have been sunk along the
tunnel’s alignment down to the level of the Canal, and from the base
of each, excavations commenced in each direction to provide
(including the two tunnel ends) forty-four working faces.
There is visible evidence that the debris hoisted up the shafts by
winding engines (horse gins) was spread over the adjacent ground.
Excavation progressed well, but it became apparent that cost was
exceeding budget and that the consortium would be unable to complete
the contract for their stated price ― the eventual cost per yard was
twice that originally estimated. The contract was therefore
liquidated, and in March 1804 Barnes again took over direct
supervision of the work, Caleb Maulin being appointed site engineer.
Maulin did not survive long in the role, being dismissed after
shortcomings appeared in his accounting; he was replaced by the
highly competent Henry Provis, who also supervised construction of
the flight of locks linking the Blisworth and Cosgrove pounds.
Surprisingly, the rate of fatal accidents on the Blisworth tunnel
project appears to have been low. So far as can be
ascertained, only two coroner’s inquests (three deaths) were
recorded in the press of the time, although the first of these
reports refers to another fatality for which no report has been
discovered; and there may have been others.
The first fatality was due to suffocation caused by ‘damp’.
Gases (other than air) in coal mines in England were collectively
known as ‘damps’, a name thought to be derived from the German
dampf
meaning vapour. If so, the term was probably introduced into
England by German miners who were brought here in the 17th century
to help develop deep mining:
“ACCIDENTS.—On Wednesday last an inquest
was taken on the Plain, in the parish of Blisworth, on view of the
body of Benjamin Ludlow, a young man employed on the Grand Junction
Canal works, who having occasion to go down a sinking pit [one
of the working shafts] on the Plain, before he had got to the
depth of ten yards called to be drawn up, but the damp had so great
an effect on him that he was instantly suffocated, and fell to the
bottom of the pit; when David Williams, a miner, attempted to go
down to his assistance, but had nearly lost his life in the attempt,
as before he had descended fifteen yards he was under the necessity
of making a signal to be drawn up, and was nearly suffocated when
taken out. The damp was so strong that it was necessary to
throw a large quantity of water into the pit, and it was an hour and
a half before any person would venture to fetch up the body of the
unfortunate youth. The Jury brought in the verdict Accidental
Death. The deceased had a brother who lost his life about two
years since, by falling down a pit, on the Plain, more than thirty
yards deep.”
Jackson’s Oxford Journal,
8th November, 1800.
The second coroner’s report investigated two further fatalities,
also at one of the tunnel’s pits:
“. . . As they were drawing two of the workmen up from one of the
shafts, by a sudden jirk (sic) of the horse, the basket in which the
men stood slipped off the hook affixed to the rope, by which
accident they were both precipitated to the bottom (a depth of sixty
yards); one of then was killed on the spot and the other survived
but a few hours.”
The Northampton Mercury,
22nd October, 1803
――――♦――――
1805 – COMPLETION
By March 1805, work on the tunnel was complete and the final section
of the Canal was flooded. On 25th March, an opening ceremony
took place with great jubilation (and the customary dinner for the
Company’s big wigs):
“That grand line of communication between the metropolis and the
most distant parts of the kingdom which the Grand Junction Canal was
to effect, was completed on Monday last, when an amazingly large
concourse of people assembled, some of them from considerable
distances, to view the stupendous works at Blisworth Tunnel, and to
see the grand procession in honour of the opening of it. One
of the Paddington packet-boats, called the Marquis of Buckingham,
was the first that went through the Tunnel. This was early in
the morning, in order to join the other boats assembled at the north
end of the Tunnel, at Blisworth, to form the grand procession.
About eleven o’clock the Committee of the Canal company (who had
superintended this great work), Messrs. Praed, Mansell, Unwin,
Parkinson, Smith, and a great number of others of the principal
proprietors, entered the boats, attended by Messrs Telford, Bevan
and other of the engineers employed on the Canal, and by a band of
music, and proceeded into the Tunnel amidst the loudest acclamations
of the spectators. The pitchy darkness of the Tunnel was
shortly relieved by a number of flambeaux and lights, but the
company in general seemed lost in contemplating the stupendous
efforts by which this amazing arch of brickwork (about eighteen
inches thick in general, fifteen feet wide and nineteen in height,
withinside, being of an elliptical form, 3080 yards in length) had
been completed between the 10th August 1793, and the 26th February
1805. The height of the hill, above the Tunnel, being, for a
considerable way, full sixty feet, for drawing up the clay and soil
which were excavated, and letting down the materials to different
parts of the works, nineteen shafts, or Wells, were sunk on
different parts of the line, and a heading, or small arch, was run
or formed the whole length, below the present Tunnel, with numerous
cross branches to draw off the springs of water, which would
otherwise have impeded the work.
In an hour and two minutes the boats with their company arrived at
the south end of the Tunnel, and were greeted by the loud huzzas of
at least five thousand persons, who were assembled, and who
accompanied the boats with continual cheers as they proceeded down
the locks to Stoke, and from thence to Old Stratford.
The principal company retired to the Bull Inn, at Stony Stratford,
and about six o’clock, 120 proprietors and friends of this grand
undertaking sat down to an excellent dinner, Mr. Praed in the chair.
The utmost harmony and conviviality prevailed among the company till
near twelve o’clock, when they broke up. All the other inns in
Stony Stratford were filled with company, and many of the parties
did not separate till a late hour.”
Northampton Mercury,
30th March, 1805
Telford inspected the Blisworth tunnel a few months later:
“This Tunnel, which was opened on the 25th day of March last, has
been laid out in a perfectly straight direction; the materials and
workmanship seem good of their several kinds, and as headings have
been driven so as to collect and conduct the water of the adjacent
grounds into directions proper for protecting the Brickwork, and
preventing injury being suffered by the goods in passing, I have no
doubt but that, with due regulation and attention in future, this
difficult and expensive work will fully answer the purposes of the
Navigation.”
The General State of the Grand Junction Canal, Thomas Telford
(1805)
The Cosgrove embankment and aqueduct were completed shortly after
the Blisworth Tunnel. Curiously, in his report Telford makes
no comment on the standard of the work, except to say that it is in
the hands of “respectable and responsible contractors . . . . and
as I have, from good authority, their assurance that every part
shall be left in a perfect state, it is unnecessary, at this time,
to enter particulars . . . .” which suggests that the great
civil engineer’s opinion was, naively as events were to prove, based
on hearsay rather than on personal inspection. One wonders
whether the Committee were satisfied with what they read. So
far as the local press was concerned:
“Grand Junction Canal.—We are happy to announce the completion of
nearly all the great works which were going on upon this important
and extensive line of inland navigation, rendered peculiarly
interesting to Englishmen by forming an immediate connection with
the British capital, and the numerous canals which intersect and
cross each other in all directions between our great manufacturing
towns and works. On Monday morning last, the stupendous
embankment between Wolverton and Cosgrove, near Stony Stratford, was
opened for the use of trade. Boats navigating the Grand
Junction Canal will now avoid the delay, labour, and danger, of
passing eight locks.”
The Northampton Mercury,
31st August 1805
――――♦――――
THE FINAL BILL
In the introduction to his inspection report of 1805, Thomas Telford
felt obliged to include a few words in justification of the Canal’s
much inflated construction cost:
“The number and magnitude of the obstacles to be overcome, united
with the rapid increase which has taken place in the value of labour
during the time the works have been under execution, must also, in a
great measure, satisfy the minds of subscribers why additional sums
have been required beyond those originally provided for the purpose
of the undertaking.”
Although the Grand Junction Canal now formed a continuous waterway
from Braunston to Brentford, with the important Paddington Arm also
in operation, its investors did not at first receive the handsome
returns that their investment was to produce in later years: [29]
“In 1806, I find the Blisworth tunnel completed, and a very
masterly and surprising work of art; the whole main line of this
canal is also completed, and some of its collateral branches; but
the communication with Northampton is by a railway: on this great
concern, (the Grand Junction Canal) £1,500,000 have been
expended; shares at present under prime cost, and dividends small,
owing to improvements still making, and paid for from the tonnage;
but hopes are entertained of its coming to pay a good interest upon
the expenditure. Reservoirs of water and other improvements
are in hand or in contemplation.”
The Agriculture of the County of Northampton,
William Pitt (1806)
. . . . and this letter dated 10th July, 1806, published in the much
respected periodical, The Gentlemen’s Magazine: [30]
“Much has of late been said in the public papers, and perhaps
with truth, of the excellence and utility of the Grand Junction
Canal; but many of your readers who have seen their puffing
paragraphs, will be surprised to hear that the benefit, if any, has
hitherto, with the exception of a few individuals, been to the
publick alone; and the original proprietors have as yet received no
advantage whatever from the concern. It is now 17 or 18 years
since the undertaking was begun; new schemes have been successively
proposed and executed, but the proprietors are still in vain
expecting their golden dreams to be realized. To the original
speculators, this may be no more than the just reward of their
views, if avarice, as it probably was with some, not the public
good, was their motive for subscribing. But so long a time has
now elapsed since the commencement of the undertaking, that many of
the first subscribers have been long dead, and their representatives
are now suffering the consequences of ill-judged speculation.
From the pressure of the times, many widows and young ladies,
whose fortunes, with the hopes of extraordinary interest, were
vested by their friends in the stock of this Company, have either
been obliged to sell their shares at a very great disadvantage and
loss, or to struggle with difficulties which could not have been
foreseen or expected . . . .”
The various applications to Parliament over the years to 1803 had
authorised the Company to raise capital far in excess of Jessop’s
initial estimate (£400,000):
Act 33 Geo. III |
1793 |
£600,000 |
36 |
1795 |
225,000 |
38 |
1798 |
150,000 |
41 |
1801 |
150,000 |
43 |
1803 |
400,000 |
|
|
|
Total |
|
£1,525,000 |
Of this, £1,404,000 was raised, but later developments were funded
from revenue that inflated the final bill to over £1,500,000, for
there was much that remained to be done to complete the full extent
of the project. The important Paddington Arm had opened in
1801, although contemporary reports suggest that, initially at
least, the facilities available to support trade at Paddington Basin
needed much development. [31] Following the
opening of the Blisworth Tunnel, the iron rails from the Blisworth
Hill plateway were reused to connect Northampton with the Canal at
Gayton; but a decade was to pass before Northampton ― and Aylesbury
also ― received branch connections to the main line. By 1806,
the Cosgrove embankment was showing signs of failure; repairs were
made, but two years later the Cosgrove aqueduct failed, severing the
canal and leading, in 1811, to Benjamin Bevan’s iron trunk aqueduct
that stands today. In places side ponds were built to conserve
water and more reservoirs and pumping stations were built,
particularly at Tring.
Despite the many calls on the Company’s exchequer during its early
years, the Canal was coming of age and starting to flourish (Appendix
II. gives a brief view of the waterway in 1813). In
1810, annual receipts amounted to £168,390 12s; in 1815, £155,000; [32]
and by 1819:
“. . . . the annual gross revenue of the canal amounted to the
sum of £170,000; it possess 1,400 proprietors; and its shares of
£100 have recently sold at from £240 to £250 each. Many of the
first capitalists in the kingdom are its proprietors, and its usual
routine of business is so conducted as to give satisfaction to all
who are connected wit it.”
A Tour of the Grand Junction Canal in 1819,
John Hassell.
Share prices peaked at almost £350 (for a £100 share) in 1824,
whilst dividends peaked at 13%, a level that was maintained for
seven years until 1832, when it fell to 12%. Following the
coming of the public railways, the Company’s share price declined to
around par and the dividend to 4%, at which levels both remained
stable for a long period. [33] By
comparison, the Oxford Canal was built before the inflationary
pressures of the French Wars, resulting in a lower construction cost
and a higher return to its investors; in 1833, that company was
paying a dividend of 32% on its £100 shares, which at the time had a
market value of £595. [34]
――――♦――――
APPENDIX I.
THE GRAND JUNCTION WATERWORKS COMPANY
1811-1904
The Grand Junction Waterworks Company was established in 1811 to
exercise the water supply rights vested in the Grand Junction Canal
Company by their Act of 1798. [35]
The Company extracted their supply from the Paddington Arm;
unsurprisingly, this water was found to be of poor quality. In
1820, supply was switched to the Thames near the northern end of the
present Chelsea Bridge, opposite the Ranelagh sewer and Westbourne
Brook. When this became known it caused a public outcry:
“. . . . that the water now taken from the Thames at Chelsea by
the Grand Junction Canal Company, and supplied to more than seven
thousand families, was charged with the contents of the great common
sewers, the drainings from dunghills and laystalls, the refuse of
hospitals, slaughter-houses, colour, lead, and soap-works,
drug-mills, and decomposed animal and vegetable substances; and that
the most eminent professions men had pronounced it to be a filthy
fluid, destructive of health . . . .”
The Hull Packet,
24th April, 1827
A campaign led by Sir Francis Burdett, M.P. for Westminster,
resulted in the appointment of the first Royal Commission to inquire
into the quality of the water to be supplied by the metropolitan
water companies. However, it was not until 1835 that powers
were granted to open a new intake at Brentford. This resulted
in the magnificent Kew Bridge pumping station. Opened in 1838,
it was equipped with a Maudslay beam engine that pumped water along
a thirty inch main for five and a half miles to Paddington.
This was the first long trunk main to be laid by any of the
metropolitan water companies.
In the 1850s the quality of drinking water was again of public
concern. Charles Dickens took an interest in the topic and in
carrying out research visited the Kew Bridge Pumping Station in
March 1850. He recorded details of his visit in his
campaigning journal Household Words, in an article published
in April 1850 entitled “The Troubled Water Question”.
The epidemiologist John Snow reported on an outbreak of cholera,
pinpointing a workhouse in Soho that had escaped the contagion
because it was supplied by the Grand Junction rather than the other
local supply.
Following the passage of the Metropolis Water Act (1852) – under
which it became unlawful for any water company to extract water for
domestic use from the tidal reaches of the Thames ― the Grand
Junction Waterworks Company again moved their intake, this time to
Hampton (Sunbury Lock) where deposit reservoirs and a pumping
station were completed in 1855.
Additions were made to the Hampton works during the remainder of the
century and in 1882 the Company began to filter part of the supply
there, thus relieving the Kew Bridge works. A large open
reservoir for filtered water was inaugurated on Hanger Hill, Ealing,
in 1888. Acts of 1852, 1861 and 1878 enlarged the area of
supply and by the turn of the century the company’s boundary
stretched from Mayfair to Sunbury.
Following the Metropolis Water Act (1902), the functions of the
Grand Junction Water Works Company were assumed in 1904 by the
Metropolitan Water Board and the company ceased to exist.
――――♦――――
APPENDIX II.
THE GRAND JUNCTION CANAL:
From:
An Historical and Topographical Account of Fulham, T.
Faulkner (1813).
THROUGH the
northern extremity of this parish runs the Paddington Canal, for
which an Act was obtained in the year 1795, communicating with the
Grand Junction Canal at Norwood. This latter canal was
executed under a Bill obtained in the year 1793, and begins at
Braunston in Northamptonshire, where it joins the Oxford Canal, and
ends at the Thames near Brentford. By this inland navigation
the metropolis is connected with all the different canals which have
been made in the midland and north western parts of England; thereby
affording a cheap and easy conveyance of all the various articles of
manufacture, and the produce of the counties through which the line
of canals passes, comprehending the great and commercial port of
Liverpool, the considerable manufacturing towns of Manchester,
Sheffield, Birmingham, Nottingham, &c. the salt mines of Cheshire,
the potteries, the coals and iron of Staffordshire and
Worcestershire, besides the great advantages resulting to the
agricultural interests of the country by the transport of lime and
various sorts of manure. Great quantities of timber for his
Majesty’s dockyards at Deptford, and for the use of ship builders in
general, are conveyed by the same channel; also government stores
and ammunition to the depot, which upon the completion of this
canal, was established on an extensive scale at Weedon. The
length of the Grand Junction Canal, with all its collateral branches
is 140 miles. The canal was not completed till March 1805,
when the Blisworth Tunnel was opened. The long interval from
its commencement until its final completion, may be attributed to
the very considerable difficulties which the undertakers had to
encounter, during the progress of the works, independent of the
excavating such a vast length of canal, which is 36 feet wide, at
the top level, 24 feet at the bottom, and 4 feet 6 inches in depth.
It required the erection of upwards of 200 bridges, the construction
of 110 locks of 86 feet in length and 15 feet in clear width, and an
average rise of 7 feet in each, requiring 9,030 cubic feet, or 250
tons of water; the forming of two tunnels, one at Blisworth and the
other at Braunston; the former of 3,080 yards in length, 15 feet
wide and 19 feet high, and the latter 2,045 yards in length and of
the same dimensions as the former.
The great range of chalk hills, near Tring, are passed by a deep
cutting, extending 3 miles in length, and the greatest depth 30
feet. In several other parts of the canal, there are likewise
deep cuttings, of considerable magnitude. The canal is carried
over the valley of the river Ouse, between Wolverton and Cosgrove,
by an embankment of 40 feet in height, and an aqueduct, which is now
constructed of iron, the former brick one, of three arches, having
fallen in in the year 1808. There are likewise embankments of
almost equal magnitude at Weedon, and at Bugbrook, besides numerous
lesser embankments and aqueducts in different places; there are
seven large reservoirs, from which, and other resources, the canal
is at all times most abundantly supplied with water. The trade
upon the canal, which is now very extensive, has been uniformly
increasing. Articles of commerce, including those of every
description, conveyed along the line in the last year, mounted to
527,767 tons. This trade, great as it now is, must soon
receive a very considerable addition from other lines of
communication, which are now forming, particularly from the Grand
Union Canal; the works of which are now in a state of such
forwardness, that they are expected to be completed by the latter
end of next year. This canal will join the Grand Junction
Canal at Long Buckby, in Northamptonshire, and the Old Union Canal
at Market Harborough; a direct inland navigation will then be formed
from the metropolis to the north eastern parts of the kingdom.
A canal is likewise now making from the Grand Junction Canal at
Marsworth to the town of Aylesbury. Another collateral branch
from the Grand Junction Canal is likewise about to be made to the
town of Northampton to join the river Nene. And in the late
sessions of parliament, a bill was obtained for extending the canal
at Paddington to the Docks at Limehouse, by which the goods brought
up by the Grand Junction Canal will be forwarded in the same boats
directly to the place of their destination, instead of being
deposited in warehouses at Paddington, and afterwards carried from
thence into the city, and to the Docks.
We have thought it necessary to draw the attention of our readers to
a work of such considerable importance as that of the Grand Junction
Canal, embracing as it does so many objects worthy the consideration
of a commercial people, and affording so many advantages to the
merchant, the manufacturer, and the agriculturist. |