|
NOTES AND
EXTRACTS
ON THE HISTORY OF THE
LONDON & BIRMINGHAM RAILWAY
CHAPTER 9
CONSTRUCTION
―
THE EUSTON EXTENSION
THE SECOND ACT (1835)
While the design and legal work necessary to build the Railway along
the route authorised in the 1833 Act was in progress, the Board had
second thoughts about the location of their London terminus.
Following some debate (initiated by Stephenson) it was decided to
change the location of the London terminus from Camden Town (the
site authorised in the 1833 Act) to Euston Grove, about a mile to
the south-east. This change required the authority of a
further Act of Parliament, a considerable investment in land, and
extensive civil engineering work necessary to cut through a built-up
area. It is to the benefit of today’s travellers that those
long forgotten Board members considered the outlay worthwhile.
On the 3rd July 1835, there passed into law . . . .
“An Act to enable the London and Birmingham
Railway Company to extend and alter the Line of such Railway and for
other Purposes relating thereto . . . .
. . . . II. And be it further
enacted, That it shall be lawful for the said Company and they are
hereby empowered to make an Extension of the said Railway . . . .
commencing in a Field on the West Side of the High Road leading from
London to Hampstead, being the Site of the Depot or Station intended
to be made for the Use of the said Railway, in the Parish of Saint
Pancras in the County of Middlesex, and thence passing across the
Regent’s Canal between the First and Second Bridges Westward of the
Lock at Camden Town into and through the said Parish of Saint
Pancras, and terminating in a vacant Piece of Ground in a Place
called Euston Grove, on the North Side of Drummond Street near
Euston Square in the same Parish, and which said Extension of
Railway will pass through or into the Parish of Saint Pancras in the
said County of Middlesex.”
5 & 6 Gulielmi
IV. Cap. lvi., RA 3rd July 1835.
Section III. of the Act also authorised alterations to the route at
Wolverton, Weedon and Brockhall, by which two tunnels and a bad
curve were avoided.
The new station faced the Euston Road, [1] which
became, de facto, the barrier for railway termini approaching
London from the north and west; King’s Cross, Saint Pancras,
Marylebone and Paddington stations are sited along the Euston Road
and its extensions.
――――♦――――
THE CAMDEN INCLINE
With an average gradient of 1:85, the ‘Euston Extension’ ― also
known as the ‘Grand Excavation’, but now generally referred to as
the ‘Camden Incline’ ― was to become the one section on the Railway
where the ruling gradient of 1:330 could not be maintained. As
built, the gradients along the sections of the Extension were:
|
Gradient, Euston to Camden.
There are 80 chains to a statute mile [2] |
|
Chains |
|
Gradient |
|
Section |
|
12 |
………… |
Fall 1 in 156 |
|
Euston to Hampstead Road |
|
13½ |
………… |
Level |
………… |
ditto |
|
16½ |
………… |
Rise 1 in 66 |
………… |
Hampstead Road to Crescent
Place |
|
17 |
………… |
Rise 1 in 110 |
………… |
Crescent Place to Park Street |
|
9 |
………… |
Rise 1 in 132 |
………… |
Park Street Bridge |
|
16 |
………… |
Rise 1 in 75 |
………… |
Park Street to Regent's Canal |
 |
|
An
artist’s impression of a roller from the Camden Incline. |
|
LONDON
AND
BIRMINGHAM RAILWAY
. . . . The stationary engine at Camden-town requiring
some trifling repair, the morning train on Saturday last
was worked up the incline by locomotive engines, which
were to take the trains on from the station last
mentioned when more than one engine is required.
In the present case it was expected that one would have
sufficed, and one accordingly was attached in front of
the train (the eleven o’clock), but a drizzling rain
falling, the power, shortly after the train started, was
found inadequate, and a second engine was despatched to
its assistance. When it reached the tail of the
train, the wheels of the engine in front unfortunately
slipped, and a partial collision occurred. It was,
however, sufficient to occasions a severe contusion on
the head of Hallam, one of the passengers in the last
carriage of the train. |
|
The Era, 30th June 1839. |
Due to its steepness and the inconvenience of manoeuvring
locomotives in the confines of the planned passenger terminus, it
was decided to work the Euston Extension, not with locomotives, but
with an endless cable system powered by a pair of stationary steam
engines. These were located at the top of the Incline at
Camden Town:
|
“This rope is ten
thousand nine hundred and fifty feet in length, seven inches in
circumference, and weighs about eleven tons twelve hundred weight;
it runs over hollowed iron sheaves, turning on an axle in an iron
frame, placed at distances of twenty-four feet. The mode,
however, in which the engineer has enabled the engine to draw the
carriages round a curve of considerable sharpness, is at once most
ingenious and beautifully simple . . . . As the curve becomes
sharper, the above pulley is placed the more out of the centre of
the line of rails over which the carriages are passing ― and the
nearer to the convex side of the turning, the guard being towards
the concave side of the wall; consequently, as the rope is fastened
to the centre of the carriage, it is drawn into the centre of the
line as the carriage passes each sheave, and when this is
sufficiently passed to allow the rope to drop by its own weight, it
falls upon the guard and slides at once into the groove of the
sheave.”
Freeling's Railway Companion, from London to Birmingham,
Arthur Freeling (1838). |
In July 1836, a tender was accepted from the engineering firm of
Maudslay, Sons and Field to supply two 60 h.p. condensing steam
engines capable of drawing trains up the Incline at 20 m.p.h.
These were installed in a subterranean engine house together with
their boilers and the winding gear they were to drive. The
only hint that the traveller had of this machinery was a pair of
tall chimneys, described by Francis Wishaw as being of “beautiful
symmetry and exquisite workmanship”. |

Camden Town Depot.
Stationary engine house in the course of erection,
by John Cooke Bourne, May 1837. The original engine house is shown
in the background.
|
In his history of the line, Peter Lecount claims that locomotives
were
capable of working the Extension, but were prevented from so doing
by the legislation, which aimed to prevent the nuisance caused by
their noise. Lecount appears to be referring to section 50 of
the 1835 Act, which, while not referring to locomotive engines
specifically, can be read to impose the restriction to which he
refers:
“L. And be it further enacted, That the
said Company shall not fix, erect, or build, or otherwise work or
use, or permit or suffer any other Person or Persons to fix, erect,
or build or otherwise suffer to be worked or used, any Steam or
other Engine, Forge or Manufactory, on any Part of the Land or
Ground purchased of and conveyed to them by the said Charles Lord
Southampton by the Deed Poll dated the Third Day of January One
thousand eight hundred and thirty five, which may be or cause any
Nuisance, Annoyance, Damage, or Disturbance to the said Charles Lord
Southampton, his Heirs or Assigns, or any of his or their Lessees or
Tenants in the said Parish of Saint Pancras, without first obtaining
the Consent in Writing of the said Charles Lord Southampton, his
Heirs or Assigns.”
5 & 6 Gulielmi
IV. Cap. lvi., R.A. 3rd July 1835.
That said, locomotives were used to work the Incline when operation
of the winding engines was suspended for repair or maintenance.
In all likelihood the noise of the heavy endless cable being dragged
over a long succession of squealing rollers was probably comparable
in nuisance to that of a steam locomotive under load. |

The stationary steam
engine chimneys and the locomotive workshops (right background), looking
towards Camden. By E. Duncan, 1838.
Barges on the Regent’s Canal are just visible below the
workshops ― the canal bridge marked the summit of the incline.

Camden Town Depot.
Locomotive Engine House, Chimneys of Stationary Engine, with rails,
eccentrics, &c. ― looking towards London. By John Cooke Bourne, 1838.
|
“The land being on a considerable rise
outwards from London is worked, as before named, by endless ropes
passing over pulleys in the middle of the tracks, which ropes are
set in motion by the stationary steam engines at Camden Town.
Great precaution is required in attaching the carriages to the rope;
and this is generally done by one man, who is trained for that
purpose. The way in which he effects the fastening is by means
of a small rope, called a ‘messenger’, having a slip knot at one
end, which he passes over the rope, and holds the other in his hand
as he stands on the foremost carriage in order to release the train
when it reaches Camden Town, or in case of accident. By a
signal given to the engineer, the engines are stopped in an instant.
The train is generally drawn up this length of railway in three or
four minutes, during which time the passenger passes under several
very handsome stone and iron bridges and galleries; the most
extensive are those under the Hampstead-road and Park-street . . . .
When the train arrives at the Iron Bridge which carries the line
over the Regent’s Canal, the carriages are detached from the rope,
and allowed to run along the line till they meet the locomotive
engine by which it is afterwards propelled.”
The London and
Birmingham Railway, Thomas Roscoe and Peter Lecount (1839).
It was during this period that the need for a signalling
system between Euston Station and the Camden stationary engine house
led (on the 25th July 1837) to a trial of Cooke and Wheatstone’s
electric telegraph, of which more in the next chapter.
However, on grounds of cost and reliability the Directors opted for
a pneumatic signalling system, which, at Euston, was used to force
air along a tube to sound an organ pipe in the Camden stationary
engine house. An identical system operated in the opposite
direction, alerting those at Euston of the impending arrival of an
up-train:
“As soon as the reeking engine-funnel of an
up-train is seen darting out of the tunnel at Primrose-Hill, one of
the Company’s servants stationed there, who deals solely in
compressed air ― or rather who has an hydraulic machine for
condensing it ― allows a portion to rush through an inch iron pipe;
and he thus instantaneously produces in the little signal-office on
the up platform of Euston Station, where there is always a signal
man watching by night as well as by day, that loud melancholy whine
which has just arrested our attention, and which will continue to
moan uninterruptedly for five minutes. The moment this doleful
intimation arrives, the signal-man, emerging from his little office,
touches the trigger of a bell outside his door, which immediately in
two loud hurried notes announces to all whom it may concern the
arrival at Camden Station of the expected up-train; and at this
moment it is interesting to watch the poor cab-horses, who, by
various small muscular movements, which any one acquainted with
horses can readily interpret, clearly indicate that they are
perfectly sensible of what has just occurred and quite as clearly
foresee what will very shortly happen to them.”
The London
Quarterly Review, Volume LXXXIV (1848).
The cable system remained in use until 1844, when it was
replaced with locomotive haulage:
“Upon trial it was found, that the locomotive engines could
surmount the inclined plane between Euston and Camden Stations with
the ordinary trains, and that with the assistance of a second
engine, the heavy trains could also be passed to Camden Station.
A saving of ten minutes in time was the result, as well as economy
in the cost of working the stationary engines and inclined-plane
rope. After numerous successful trials, the engines and rope
were, in April, 1844, abandoned, and in course of time the
stationary engines were sold, and they are now doing duty in a flax
mill in Russia.
The saving in time thus effected was of little, or no value; and
attention being directed to the locomotive stock, it was found, that
even with two engines, the required speed could not be attained with
the heavy trains. A number of locomotive engines of large
dimensions were ordered, and by degrees the stock has been brought
to consist almost entirely of this class.”
Paper by R. B.
Dockray published in the Proceedings of the Institution of Civil
Engineers, Volume 8
(1849). |
――――♦――――
BUILDING THE EXTENSION

Excavation at Park Village,
showing the work in progress.
John Cooke Bourne, September 1836.
|
“The first shock of a great earthquake had,
just at that period, rent the whole neighbourhood to its centre.
Traces of its course were visible on every side. Houses were
knocked down; streets broken through and stopped; deep pits and
trenches dug in the ground; enormous heaps of earth and clay thrown
up; buildings that were undermined and shaking, propped by great
beams of wood. Here, a chaos of carts, overthrown and jumbled
together, lay topsy turvy at the bottom of a steep unnatural hill;
there confused treasures of iron soaked and rusted in something that
had actually become a pond. Everywhere were bridges that led
nowhere; thoroughfares that were wholly impassable; Babel towers of
chimneys, wanting half their height; temporary wooden houses and
enclosures, in the most unlikely situations; carcases of ragged
tenements, and fragments of unfinished walls and arches, and piles
of scaffolding, and wildernesses of bricks, and giant forms of
cranes, and tripods straddling above nothing. There were a
hundred thousand shapes and substances of incompleteness, wildly
mingled out of their places, upside down, burrowing in the earth,
aspiring in the air, mouldering in the water, and unintelligible as
any dream. Hot springs and fiery eruptions, the usual
attendants upon earthquakes, lent their contributions of confusion
to the scene. Boiling water hissed and heaved within
dilapidated walls; whence, also, the glare and roar of flames came
issuing forth: and mounds of ashes blocked up rights of way, and
wholly changed the law and custom of the neighbourhood. In
short, the yet unfinished and unopened Railroad was in progress . .
. . ”
Dombey and Son,
Charles Dickens (1846-8).
On the 9th December 1835, William and Lewis Cubitt were awarded the
contract to build the Euston Extension [3] for the
sum of £76,860, [4] the contract including a
penalty to be invoked should the work not be complete by the 1st
January 1837. Stephenson appointed Charles Fox Resident
Engineer although he, himself, maintained a close interest in the
progress of the work. |
|
 |
|
Above: Park Street, Camden Town, 18th
September 1836.
Below: Park Village, 26th August 1836.
|
|
 |
|

Park Street Bridge.
Note the endless cable in
the centre of the track and the railway ‘policemen’, forerunners of
today’s signalmen. |
|
Partly to economise on land purchase and bridge construction (along
its short length, the line originally passed under seven bridges)
most of the Extension lies in a walled cutting, the walls being of
stronger than usual construction throughout. The thickness of
the walling can be seen in Cooke Bourne’s drawing below.

Hampstead Road Bridge from the Camden
side.
John Cooke Bourne, 11th August
1836.
LONDON FIXED ENGINE
PLANES. ― From the Euston station to
the Camden depot there are four lines of way, which are carried as
far as Park Street between retaining walls: the clear width occupied
here is about 56 feet; the walls are about 19 feet in height, and
are built to a curved batter, with a radius of about 60 feet, the
versed sine being about 4 feet 10 inches; lowest part of the
foundation is 7 feet from the level of the rails; the thickness of
brickwork decreases from the footings upwards, being at the bottom 3
feet 11½ inches, and at the top 2 feet 7½ inches. The whole
length of these extends to upwards of 2,200 yards.
In this length there are seven bridges and archways over the
railway, each of which is in two spans. Some of these bridges
are built of brick and faced with stone; and others have iron ribs
resting on brick piers.
From Park Street to the Regent’s Canal bridge at Camden Town the are
near the general surface of the ground; and the railway is enclosed
on either side with neat iron railing and pedestals of brick resting
on dwarf walls.
As these planes are considerably curved in some portions, both
vertical sloping sheaves are used for the rope; they are fixed in
cast iron cases embedded in the ballasting.
The Railways
of Great Britain and Ireland, Francis Wishaw (1842).
Due to the section between Park Street and the Hampstead Road being
driven through London clay, Stephenson’s specification laid down
exactly how the excavation was to proceed ― on no account was the
its face to be carried on more than 40 feet in advance of the
completed retaining wall without the Engineer’s written permission.
This stipulation took into account the characteristic of London clay
to stand for a short time after being cut, but then to bulge
outwards with force as it absorbed moisture:
“One of those extraordinary difficulties to
which cuttings through the London clay must ever be liable, occurred
in this excavation. To facilitate the removal of the material, a
gullet
had been formed and a temporary railway laid down, when a season of
excessive wetness set in; the works however proceeded with that
perseverance which characterises the resident engineer Mr. Fox ―
when one morning the treacherous material gave way, the gullet was
filled up, and the labour of weeks (estimated at a cost of about
£800) was destroyed in a night, by an accident which could not have
been anticipated, as no previous experience had enabled engineers or
directors to provide a preventative, or to expect such a result . .
. . One hundred and eighty thousand cubic yards of clay were removed
from this cutting. During the progress of this portion of the
line, the Company had no less than 1,000 men employed upon this mile
and a quarter of ground.”
The Railway
Companion, from London to Birmingham, Arthur Freeling (1838).
The plans and specifications for the Extension illustrate the
substantial construction of its retaining walls:

Bridge for
intended street on the Duke of Bedford’s estate upon the Exn. L & B
Railway.
The retaining wall, shaded grey, is typical of those built along the
Extension.
“Sections
and Elevations of the Retaining Walls are shewn on the various
drawings.
The faces of these walls will be a Curved
Batter; [5]
the radius of this batter will be 50 feet, giving an average batter
of 2 inches per foot on 20 feet in every case, excepting in the
walls from Crescent Place to Park Street, which have a radius of 61
feet 8 inches, being an average batter of 2 inches to a foot on 20
feet. The whole of the brickwork of the walls will be laid in
courses radiating from the supposed centre of the curve of the
batter. The walls will increase in thickness the nearer they
are to the foundations, by half brick offsets, and the footings will
consist of steppings of two courses of brick, projecting one quarter
of a brick.
One foot thickness of Concrete will be placed under the footings of
the walls, it will project 6 inches from the footings in the front,
and be flush with the neat work behind.
The space at the back of the walls shall be well Punned [6]
in with clay. The faces of the walls will be broken at
intervals of 16 feet, or thereabouts, as near thereto as consistent
with dividing a given length of wall into an equal number of parts,
by Pilasters 4 feet by 4 inches wide, projecting half brick, built
and bonded with the rest of the wall. Counterforts [7]
will be built at the back of the wall, equidistant between the
pilasters and bonded into the wall. A stone plinth 6 inches
thick must be built in at the required height, and the wall above it
will recede ¼ of a brick from the face of the plinth.”
An extract from
Stephenson’s work specification, published in Railway Practice,
S. C. Brees (1838).
In addition to the work involved in excavating and walling the
Extension, the line passed under seven road bridges and crossed the
Regent’s Canal on an iron bowstring bridge, probably designed by
Charles Fox . . . .

The Regent’s
Canal Bridge.
“The earliest railway bridge on the
bowstring principle is that over the Regent’s Canal, near Chalk
Farm, on the London and Birmingham Railway.
It is composed of three main ribs of cast-iron open panel work,
whose outline is parallel, but which includes an arc extending to
its extremities of length and depth, and intersecting the vertical
bars which form the panels. The span is 50 feet and the height
of the ribs 10 feet. The section of each rib is in the form of
a hollow rectangle 2 feet 11 inches wide, and the space between its
sides is filled with diagonal bracing-frames 5 feet 10 inches apart.
The railway is carried by cast iron girders of the fish-bellied
shape, 28 feet between bearings and 1 foot 10 inches deep in the
middle; they are suspended from the bracing-frames in the main ribs
by wrought-iron suspension rods 2¼ inches diameter; there being
sockets in the bracing-frames to receive their upper ends, and in
the ends of the cross-girders to receive their lower ends.
The centre main rib performs double duty; and its bracing-frames
have double sockets, and carry two suspension rods. In
addition to the ribs themselves in resisting the strain of the load
there are longitudinal tie-bars under each rib, there being four
under each outside rib in a horizontal row, and eight under the
centre rib in two horizontal rows. These tie-rods are secured
to the bearing ends of the main ribs, and are in three lengths, each
united by sockets, gibs, and keys. Upon the cross-girders are
oak sleepers for the rails; and the entire space between the rails
is filled in with cast-iron plates perforated in the form of
trellis-work. The outsides of the outer ribs are ornamented
with cast-iron mouldings and fret-work. This bridge is of very
bold design and certainly a novelty as regards construction.”
The
Encyclopaedia Britannica, Vol. 12 (1856).
Alas, this fine bridge is long gone:
“The works associated with the original
station included bridges to carry various existing roadways over the
line and to carry the line over the Regent’s Canal. Of these
bridges, three are illustrated and described by Simms. [8]
They are the Stanhope Place Bridge, the Park Street Bridge, and the
bridge over the Regent’s Canal. The Stanhope Place Bridge,
consisting of two segmental masonry arches, was removed when
Stanhope Place was diverted into Mornington Terrace in the
’nineties. The Canal bridge has also been destroyed, but that
over Park Street still exists, as does that carrying Granby Terrace.
The two-arched Ampthill Square road bridge was taken down in 1898
and replaced by girders. The bridge over Wriothesley Street,
the first to be built, had been demolished as early as about
1846-47, when Wriothesley Street was closed. The cutting
running south for a short way from Park Street and spanned by
segmental cast-iron struts, is the original structure of 1836-37.”
Survey of
London: volume 21: The parish of St Pancras part 3 (1949). |

Above: the iron bridge over the
Hampstead Road.
Below: the same bridge under
construction. George Scharf, May 1836.


View taken from
under the Hampstead Road Bridge,
Looking towards the station at Euston Square, 18th September,
1837.
|
|
 |
|
The
Hampstead Road Bridge. |
“From Euston Square to
Camden Town the Railway is formed by a wide cutting or trench, about
eighteen or twenty feet deep, the sides of which are composed of
beautifully executed brick work, having an iron balustrade at top,
which when the trees and shrubs of the adjoining gardens have sprung
up, will form a pleasing object . . . . The whole of this
length is excavated from the London clay; and the walls which form
the sides are curved, in order to resist the inward pressure; they
are as much as three bricks thick at the top and seven at the
bottom; the number of bricks used in forming these gigantic walls
was about sixteen millions.”
The London and
Birmingham Railway, Roscoe and Lecount (1839).
By July 1837, the Euston Extension was complete and the first
experimental passenger journey to be made on the London and
Birmingham Railway took place. It was not without incident ―
from the casual manner in which derailments are referred to, it
seems that they, at least, were not uncommon:
LONDON AND BIRMINGHAM RAILWAY.
“Thursday week the directors gave an excursion to a select
party of their friends by way of experiment preparatory to the
public opening of the railway from the station at Euston grove to
Box-moor and back.
At one o’clock (the hour
appointed for starting) a train, consisting of eleven carriages,
left the station, gliding, by its gravity, down a gently inclined
plane for 200 or 300 yards, when the engine was immediately
attached, amidst the loud and hearty cheers of a great number of
spectators outside the line. The distance (25 miles) was
performed in an hour and eight minutes. At Box-moor an elegant
lunch was provided for the company in an marquee pitched on a
neighbouring rising ground. The weather was fine, and every
one seemed delighted with the scene. A second train of twelve
carriages left town at two o’clock, and reached Box-moor at few
minutes after three.
The train which started at one
left for town at four; but in consequence of some mismanagement as
to the supply, we believe, of water to the boiler, and the wheels of
the engine getting off the rail, sundry stoppages occurred by the
way, which protracted its arrival till ten minutes to six.
Just as this train had reached the terminus at the back of Euston
square, the engine having been disengaged, but the impetus still
continuing at a considerable velocity, the men whose duty it was to
check the motion by working what are technically called the
‘breaks,’ not being sufficiently expert, or miscalculating their
power, the carriages came with frightful force against the barrier
wall at the extremity of the line, dashing it to atoms, and causing
a rebound which frightened all and damaged not a few. The
concussion was so great that those sitting opposite in the different
carriages being thrown against each other with great violence, we
are sorry to say some instances of serious injury occurred.
Among others Lord Hatherton received a severe bruise on the cheek;
Mr. N. Calvert, formerly M.P. for Hertfordshire, violent contusions
on the face; two gentlemen and a lady had their noses broken; others
lost their front teeth, and several sprained their wrists and arms.”
The Bucks Herald, 22nd July 1837.
Other than giving a couple of clues, the article’s author fails to
mention travelling over the Camden Incline. After the
stationary engine had hauled the train up the Incline from Euston,
the writer’s reference to “gliding by gravity, down a gentle
incline plane” refers to the final section beyond the Regent’s
Canal bridge, down which the carriages descended under gravity to
Camden Depot where a locomotive was attached. On the homeward
journey the locomotive was detached near the top of the Incline.
The coaches were then pushed to its summit, from where they
descended to Euston under gravity, the descent being controlled by
the carriage brakes ― or in this particular case, by collision with
the barrier wall.
――――♦――――
FURTHER PROBLEMS WITH LONDON CLAY
In Railway Practice, Dempsey drew on examples to provide
sound advice on the dangers of earth swelling when saturated, even
when retained by substantial brickwork:
“Many
instances are recorded of the failure of these structures, which has
commonly resulted from the saturation and consequent swelling of the
earth behind them; and these effects have occurred frequently,
despite the most judiciously-selected forms and materials, and the
best attainable system of back drainage. Indeed, unless the
material be adapted to stand by itself, be thoroughly impervious to
water, or so completely drained that very little reaches the back of
the wall, it is certain that this uncontrollable agent will make its
way through the work, and produce sooner or later the disastrous
consequences which have already marred the designs of railway
engineers.”
The Practical
Railway Engineer, George Drysdale Dempsey (1855).
The Primrose Hill Tunnel was not to be Stephenson’s only run-in with
London clay. By 1843 (six years after the Extension had
opened), the clay to the rear of the Extension’s western wall had
become saturated through inadequate drainage. Such was the
force it then exerted, and despite great care having been taken in
the wall’s design, sections of it were thrust forward. The
remedy that Stephenson applied was improved drainage, to which he
added reinforcing struts between the facing walls at top and bottom,
and vaults behind the upper sections of the western wall:
“This
excavation intersects the London clay, the dip of which at that part
inclines downwards towards the east. The consequence is, that
the wall on the west side is required to sustain constantly an
enormous thrust, which is, of course, much increased when the clay
becomes swollen by absorbing water from the western environs lying
towards Primrose Hill, which are above the level of the top of the
cutting. This wall of the excavation, although built of great
thickness, with a curvilinear batter, substantial footings, and
bedded and backed in good concrete, and withal, carefully built,
showed early symptoms of its inability to withstand the pressure
acting behind it; and the upper part of the wall, the weakest,
becoming displaced to a considerable extent (in some instances more
than 12 inches), it was deemed necessary to adopt the ready means of
a temporary support offered by timber shoring.
Meantime, holes of 6 or 8 feet in length, and 3 inches in diameter,
were bored through the wall and the backing, and inclining upwards
by the apparatus known as ‘Watson’s Boring Machine’; and the
perforated tubes used by the inventor of that machine were then
introduced, and fixed into the wall. By this precaution much
of the water was prevented from accumulating within the clay; and in
some parts the clay appeared to be in some degree drier than it was
previously; but in other parts the frequent discharge of water
through the wall showed the activity of the mischievous agent, and
it became highly necessary to adopt so permanent method of giving
support to the failing wall, and preventing any further alteration
of its position.
Under the able direction of Robert Stephenson, Esq., the Consulting
Engineer to the Company, and R. B. Dockray, Esq., the Resident
Engineer, three measures were promptly adopted, which have been
found to answer their purpose admirably. These measures were:
First, introducing cast iron girders of a large section
between the eastern and western walls, so as to serve as abutments
for the latter against the former.
Second, embedding strong wooden horizontal foot-struts
between the footings of the two walls, so as to prevent the lower
part of the western wall from yielding forward, when the upper part
was strengthened by the cast iron girders.
Third, reducing the weight pressing against the western wall
by excavating the clay, and constructing spacious vaults with strong
walls.
Besides these arrangements, a large side drain was constructed near
the western wall, which drain received the water, by means of cross
channels formed with drain-tiles, from the clay behind the wall;
perforations in the wall being formed for that purpose.”
Discussion at the
Institution of Civil Engineers, reported in The Practical Railway
Engineer, G. D. Dempsey (1855). |

Drawing showing
remedial action in the Euston Extension following damage to the
retaining walls by saturated London clay, ca. 1842-3.
The diagram shows, on the western side, the vaults; also the
cast-iron girders placed across the cutting, braced with transverse
cast-iron struts.
From Railway Practice, by J. D. Dempsey (1845).
|
The above (time ravaged) drawing illustrates the remedial action
that Dempsey describes;
note also (on the plan) the cast-iron bracing between the girders.
――――♦――――
DEVELOPMENTS AT CAMDEN DEPOT
Because the decision to extend the line from Camden Town to Euston
was taken shortly after the 1833 Act had been obtained, Camden never
developed into a major passenger station ― it did, however, become a
major depot. Other than housing the stationary steam engines
and winding gear for working the Incline, Camden fulfilled a number
of other important roles, particularly with regards to goods
traffic:
“The works on the old station
were,
1st, the stationary engine-house, which
consisted of vaulting under the railway adjoining the Regent’s
Canal; the boiler-houses opening to the railway, and two very
handsome chimneys, which formed conspicuous objects in the district.
Two condensing engines of 60 H.P., built by Messrs. Maudslay and
Field, were used to draw the trains from Euston up the inclined
plane, (averaging 1 in 85) to Camden Station, whence they proceeded
on their journey by locomotive power.
2nd. A locomotive engine-house capable of
accommodating fifteen engines, together with the requisite fitting
shops and offices.
3rd. Sixteen coke ovens.
4th. Two goods sheds and stabling, together
with a small accommodation for stores, and a shop for repairs of
waggons.”
Paper by R. B.
Dockray published in the Proceedings of the Institution of Civil
Engineers, Volume 8
(1849).
Some of the Company’s offices were also located at Camden in,
it would seem, insalubrious surroundings:
“After
serving a few months in the audit office, and in the opening of the
through line to Birmingham, I was drafted from the Manager’s office
to Camden Station, in connection with the Stores and Construction
Departments. This was a change for the worse as regards my
personal comfort. The office was a rough wooden erection, with
an earthen floor, and contained, by day, myself in my great coat,
the stores of all kinds, a table, a small cabin stove, and the mice.
Chalk Farm was in the country then, and I had to prepare my meals at
the small stove, and to consume them assisted by the mice, who
evidently had a great contempt for my presence. The place was
always muddy. The station had been raised from the road by the
earth from the Primrose Hill Tunnel, and this new clay produced a
Slough of Despond, which I have only seen equalled at the Royal
Agricultural Show, at Kilburn, a few years ago.”
Fifty Years on
the London & North Western railway, David Stevenson (1891). |

Camden Depot in 1839.
The section in blue is
the Regent’s Canal.
This map is
reproduced by kind permission of Peter Darley,
Camden
Railway Heritage Trust.
As the Company gained experience in operating a trunk
railway and as the volume of goods traffic increased, in common with
most of the stations along the line, Camden’s function and layout
changed considerably during its early years . . . .
. . . . The whole of these works, (except those of a temporary
nature) were constructed in the most substantial and permanent
manner. In the design every pains was taken to anticipate the
wants of the traffic; yet such has been the rapid development of the
railway system, that in the lapse of ten years from the opening of
the line, it has been found necessary to sweep away almost every
vestige of these works, and entirely to remodel the station.”
Paper by R. B.
Dockray published in the Proceedings of the Institution of Civil
Engineers, Volume 8
(1849).

Bury 2-2-0 No. 32 leaving the
original Camden engine house,
by John Cooke Bourne, May 1839.
This locomotive was built by Mather
Dixon & Co. of Liverpool.
“The locomotive engines’ station at the
Camden depot is a rectangular building of brick, enclosing an open
quadrilateral space, and is situate on the right side of the railway
going from London, and near to the high chimneys belonging to the
fixed engines. The entrance to this station is by branches
from the main line, which pass under two archways in front of the
structure; in each of these gateways is an engine turn-table, and a
water-column on either side of the way, and above is fixed a large
tank.”
The Railways
of Great Britain and Ireland, Francis Wishaw (1842).
“As
soon as an engine has safely dragged a passenger-train to the top of
the incline at Camden Station, at which point the coupling-chains
which connected it with its load are instantly unhooked, it is
enabled by the switchman to get from the main line upon a pair of
almost parallel side rails, along which, while the tickets are being
collected, it may be seen and heard retrograding and hissing past
its train. After a difficult and intricate passage from one
set of rails to another advancing or
‘shunting’
backwards as occasion may require, it proceeds to the fire-pit, over
which it stops. The fireman here opens the door of his
furnace, which by a very curious process is made to void the red-hot
contents of its stomach into the pit purposely constructed to
receive them, where the fire is instantly extinguished by cold water
ready laid on by the side. Before, however, dropping their
fire, the drivers are directed occasionally to blow their steam to
clean; and we may further add that once a-week the boiler of every
engine is washed out to get rid of sediment or scale, the operation
being registered in a book kept in the office. After dropping
his fire, the driver, carefully taking his firebars with him,
conducts his engine into an immense shed or engine-stable 400 feet
in length by 90 in breadth, generally half full of locomotives,
where he examines it all over, reporting in a book what repairs are
wanting, or, if none (which is not often the case), he reports it
‘correct’. He then
takes his lamps to the lamp-house to be cleaned and trimmed by
workmen solely employed to do so, after which he fetches them away
himself. Being now off duty, he and his satellite firemen go
either to their homes or to a sort of club-room containing a fire to
keep them warm, a series of cupboards to hold their clothes, and
wooden benches on which they may sit, sleep, or ruminate until their
services are again required; and here it is pleasing to see these
fine fellows in various enjoying rest and stillness after the
incessant noise; excitement; and occasional tempests of wind and
rain; to which ― we say nothing of greater dangers ― they been
exposed.”
Quarterly
Review, Volume LXXXIV (1848).
Edward Bury’s weak-winded 4-wheeled engines were soon rendered
obsolete by developments in locomotive engineering, and were
eventually replaced with more powerful 6-wheelers. One outcome
from this change was that the turntables in the original engine
house were rendered too short to handle their longer replacements,
while the building was too small to accommodate anything larger.
To complicate matters further, a reduction in freight rates during
1845 led to a sudden increase in the volume of goods passing through
Camden. The outcome was that in order to enter or leave the
engine house, locomotives had to cross lines that were being used
increasingly to marshal freight trains, while down passenger trains,
which no longer needed to stop at Camden to acquire their locomotive
(the stationary winding engine having by now been abandoned),
were crossing the yard at speed. These factors combined to
heighten the risk of collision:
“THE ACCIDENT
ON THE LONDON AND BIRMINGHAM
RAILWAY . . . . The mail train which
leaves Birmingham (having previously arrived from Liverpool) at
fifty-five minutes after twelve, at night, is due at the London
terminus at thirty-two minutes after five. About a quarter
past five on Tuesday morning this train arrived at the Chalk-farm
end of the tunnel, and proceeded at full speed onwards towards the
platform at the Camden station. The train, which consisted of
from ten to sixteen carriages, including the trucks and post-office
vans, continued its progress until arriving on the London side of
Chalk-farm bridge, where the down luggage train, which was some few
minutes behind its time, was crossing from the branch curve lines
leading to the luggage storehouses on to the main line. The
fog was so thick that it is described as utterly impossible for any
one to see beyond twenty of thirty feet, and the result was, that
before any measure could be taken to stop the speed of the mail
train, it ran into the luggage train, dashing three of the luggage
vans, and three of the carriages in the mail train, literally to
atoms.”
Morning
Post, 31st July 1845.
Changes were necessary. Widening the Chalk Farm Bridge allowed
extra lines to be built into the Depot, thereby helping to separate
passenger traffic from other activities. In 1846, the original
engine house was replaced by two new buildings at opposite sides of
the yard for handling passenger and ‘luggage’ (goods) locomotives
respectively. The goods engine house, known today as the
‘Roundhouse’, is one of the few buildings from the Railway’s early
years to survive:
“The goods engine-house is circular, and
160 feet in diameter, having twenty-four lines of railway, each
sufficient for an engine and tender, radiating from a central
turnplate 41 feet in diameter. This form of building was found
best adapted to the situation in which it is placed. The
turnplate is one of Handcock’s,
made by Messrs. Lloyds, Foster, and Co.; the struts and beams are of
oak. To guard against damage to this table, from engines
running upon it from any line not corresponding with that on the
revolving top, a strong casting is fixed round the periphery of the
top, and projects upwards to the level of the rails. This
casting has no apertures for the flanches of the wheels, except at
the ends of the rails upon the table itself; thus an engine cannot
easily be run upon it, except when the revolving top is so turned
that the two sets of rails shall correspond.”
Paper by R. B.
Dockray published in the Proceedings of the Institution of Civil
Engineers, Volume 8
(1849). |

The goods engine house at Camden,
known today as the ‘Roundhouse’.
The conical slate roof has a
central smoke louvre (now glazed) and is supported by 24 cast-iron
Doric columns arranged
around the original locomotive
spaces and a framework of curved ribs.

Camden Depot in 1847
Reproduced by
kind permission of Peter Darley,
Camden
Railway Heritage Trust.
|
After about a decade in use, the Roundhouse also became too small to
fulfil its intended role. Over the decades that followed it
served various unrelated purposes, including some 50 years as a
bonded store for Gin distillers W. & A. Gilbey Ltd. In recent
years the building has become associated with the performing arts .
. . .

Restored to something of its original condition, the Roundhouse is
now regarded as a notable example of mid-19th century railway
architecture and, as such, was declared a National Heritage Site in
2010.
|
CHAPTER
10
――――♦――――
|
FOOTNOTES. |
|
1. |
Euston Road was then known as ‘The New
Road’. In 1852, the central section of The New Road, between
Osnaburgh Street and Kings Cross, was renamed Euston Road, the
eastern section became Pentonville Road and the western section
Marylebone Road. |
|
2. |
For surveying, the
statute mile is divided into eight furlongs; each furlong into ten
chains; each chain into four rods (also known as poles or perches);
and each rod into 25 links. This makes the rod equal to 5½
yards or 16½ feet in both Imperial and U.S. usage. |
|
3. |
Stephenson’s plan
for Euston Station had been approved in the previous month. |
|
4. |
Roscoe and Lecount, who state the outturn
was £91,528. |
|
5. |
“BATTER: the face
of a retaining or other wall when built in a leaning position, the
top part falling back within the line of base; walls of this
description are sometimes termed, ‘tallus walls’. The batter
of a wall is either straight or curved; the latter are also
generally commenced straight from the top, the greatest degree of
curvature being given to the bottom of the wall. The average
rate of the batter of the walls upon the London and Birmingham
Railway is 2½ inches to the foot, and 1 inch to the foot for the
wing walls of bridges.”
From
A Glossary of Civil Engineering, S. C. Brees (1844). |
|
6. |
“PUNNING: a mixture of good tempered clay
and sand reduced to a semi-fluid state, and rendered impervious to
water by manual labour, as working and chopping it about with
spades. It is used for the purpose of retaining the water in
any particular situation, or for excluding it from any works: and it
is usually spread in layers of about 12 inches in thickness.”
From
A Glossary of Civil Engineering, S. C. Brees (1844). |
|
7. |
“COUNTERFORT:
a pier or buttress, generally applied at the back of retaining walls
in modern civil engineering, for the support of the same, and
likewise for the purpose of forming a tie to the material at the
back of the wall. Counterforts are also sometimes carried up
upon the face of a wall.”
From
A Glossary of Civil Engineering, S. C. Brees (1844). |
|
8. |
F. W. Simms, Public Works of Great
Britain (1838). |
|